Before the
13th
floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005.
Tel. 22163964 /
22163965, Fax No. 22163976
E-mail mercindia@mercindia.com
Website: www.mercindia.com
In the matter of
Petition filed by M/s RHT
Consutructions, Dhule under Section 29(1)(c) and (d) of the ERC Act, 1998
regarding consumer’s options for ORC Scheme.
Shri Jayant Deo, Member
Dr Pramod Deo, Member
Dated: March 24, 2003
Shri T.K.
Agarwal of RHT Constructions, At Post Shirpur, Tal & District Dhule has
submitted an application dated 17.12.2002 seeking that the Commission direct
the Respondent Board (MSEB), in exercise of its powers under Sec. 29 and
Sec. 22(1) (c) & [d] of the ERC Act, not to compel either the builder or
his individual customers or group of customers to opt for ORC Scheme, and to
provide quotation and electricity connection to individual customers as and
when they submit the application form, without
unreasonable delay, and without waiting for the applications of all the
customers in that building. He has
also sought "all other reliefs in favour of the petitioner which are
necessary for the effective adjudication of this petition".
2. Hearing for admission was held on 20th
February 2003. Shri S.C. Karandikar,
Counsel for the Petitioner, submitted that his client is a builder who has
completed two constructions, viz. Ramdevi Complex and Balaji Complex, with 147
tenements. Counsel submitted that the petition relates to the procedures
adopted and charges applied to new connections, particularly for apartments and
commercial complexes. He has constructed the buildings for sale and, as per the
conditions of sale of the premises, the individual buyers are required to apply
for the electricity connection to MSEB, although the Petitioner would extend
all possible help to them. However,
MSEB have issued a common quotation dated 4.1.2002 to the Petitioner for
payment of Rs.7,10,854/- as Service Line Charges (SLC) for creating the
infrastructure required such as sub-station,
cabling from the transformer to the individual metering points,
etc. Counsel pointed out that, apart
from the above, MSEB would be recovering SLC charges from the individual
consumers.
3. Counsel for the Petitioner cited Section
18(a) of the Electricity (Supply) Act, 1948, which provides that “subject to
the provisions of this Act, the Board shall be charged with the following
general duties, namely … in the most efficient and economical manner with
particular reference to those areas which are not for the time being supplied
or adequately supplied with electricity.”
Therefore, a statutory duty has been cast upon MSEB to provide
electricity by creating appropriate infrastructure such as generating stations,
transmission & distribution lines, etc.
MSEB have also earmarked budgetary allocations for such activities in
their tariff proposal before the Commission. He referred to page 58 of Vol-I of
the tariff proposal, which shows that a provision of Rs.1,624.31 crore has been
earmarked for addition of assets, which includes Rs.700 crore for distribution.
Therefore, MSEB should not demand from consumers any amount for further
infrastructure development since it is taken care of through the tariff. In addition, MSEB collects fixed Service
Connection Charges for release of individual connections over and above SLC
charges for strengthening or providing infrastructure. Thus, MSEB obtains funds for the same
infrastructure through budgetary provisions reflected in tariff proposals, from
the builder or developer, and also from individual customers. Counsel submitted that the Petitioner is not
against MSEB recovering the amount required for infrastructure, but objects to
the manner in which it is collected through different types of charges and
accounting heads for the same work.
4. Counsel for the
Petitioner also pointed out that, after persistent efforts to obtain
clarification or furnish a copy of the circulars / guidelines on the basis of
which the charges were quoted, MSEB issued a fresh quotation on 2.12.2002 for a
reduced amount of Rs.4,80,000/-, which indicates the arbitrary manner in which
MSEB is levying such charges.
5. Counsel for the Petitioner argued that
the Commission is empowered to act on the present petition under Section
22(1)(a) & (b), Section 29 of the ERC Act, 1998. He also referred to Regulation 72(2) of the MERC (Conduct of
Business) Regulations, 1999, which states that “No utility shall fix any
tariff for intra-State transmission, distribution or supply of electricity and
terms and conditions for the supply of electricity, without the general or
specific approval of the Commission.”
He submitted that in view of Commission’s Order in Cases 10 and 11 of
2000 (applications of (i) Maharashtra Chamber of Commerce & Industries,
Mumbai, and (ii) Akhil Bharatiya Grahak Panchayat, Pune) in the matter of
Commercial Circulars and the Clauses of Conditions and Misc. Charges for supply
of electrical energy issued by MSEB without prior approval of the Commission,
the latter has jurisdiction and may admit the petition.
6. Counsel for the
Petitioner clarified that since the project site falls within the Shirpur Gram
Panchayat area, Commencement Certificate and other such requirements are not
applicable as would be the case in Municipal areas.
7. Shri S.K. Sen,
Counsel for the Respondent (MSEB) submitted that the issue does not relate to the
procurement process, nor does it fall within the scope of Section 22(1)(c) or
(d) of the ERC Act. Since this is
essentially a matter between the purchasers of the premises and the builder,
the Commission is not the appropriate forum for such dispute resolution. The Petitioner has a commercial interest
which is in conflict with that of the prospective buyers of the premises. Moreover the Petitioner is asking MSEB to
collect the appropriate amounts from his customers, who are not represented at
the hearing as parties. Therefore, on
this ground itself, the Petition has no merit and should be rejected.
8. MSEB’s Counsel drew attention to the
Petitioner's written submission that “various
prospective customers have contacted the petitioner and have principally agreed
to purchase the same but the transactions have not materialized for want of
availability of electricity connections.”
Counsel stated that there has been no compulsion on the builder to pay,
but that he is not assuming his consequential responsibility after applying for
connections. He submitted that the
Petitioner was fully aware of the total load requirement while preparing the
building plans and seeking approval from the Gram Panchayat. He initially asked for a 200 kVA
transformer, and subsequently revised it to 100-kVA stating that the load can
be upgraded at a later stage as and when it increases. Counsel also pointed out that the
Petitioner, vide letter dated June 27, 2001, has given a written undertaking to
pay the required charges. However, Counsel admitted that due to these changes
and other administrative difficulties and procedures relating to the sanction
of material, etc., the matter had been delayed considerably.
9. Counsel for MSEB submitted further that the SLC
matters are a part of the Terms and Conditions of Supply regarding which
matters are pending before the High Court, and a judgement is expected
shortly. Hence it would not be
appropriate at this stage to hear the matter, being subjudice.
10. In reply, Counsel for
the Petitioner submitted that, pending the High Court’s decision in the SLC
matters, the Commission may admit the petition considering the Commission's
jurisdiction, and the case would thereafter take its own course based on the
High Court orders.
11. The Commission
observed that since the present application arises out of a dispute between the
builder and the prospective purchasers of the premises, it does not fall within
the scope of the ERC Act, 1998, and has no merit. However, if the Petitioner desires to petition the Commission on the SLC matters after
pronouncement of the judgement of the High Court, he may do so at the
appropriate time, and such petition would be dealt with separately. The Commission, therefore, does not see any
merit on the prayer of the Petitioner and disposes of it accordingly.
| Sd/- | Sd/- | Sd/- | |
| (Jayant Deo) | (Dr Pramod Deo) | (P. Subrahmanyam) |
|
| Member | Member | Chairman, MERC |
|
| (A.M. Khan) | |||
| Secretary, MERC | |||
| Bombay, March 24, 2003 | |||
|
|||