To view copy of Event Notice Click on Underlined
HOUR
|
|
|
11:00 |
Petition
of REDAM under Section 42 (3) of the EA, 2003; Regulations 3
and 18 (2) of MERC (Distribution Open Access) Regulations 2005;
and Regulations 92 - 94 of the MERC (Conduct of Business) Regulations,
2004 for adjudication of Dispute regarding provisions of non
discriminatory open access.
[Case No. 10 of 2011] |
 |
| |
11:00 |
Petition
of M/s Ispat Industries Limited for Open Access under the provisions
of the Electricity Act, 2003, the MERC (Distribution Open Access)
Regulations, 2005, MERC (Transmission Open Access) Regulations,
2005 and procedure for Distribution Open Access.
[Case No. 68 of 2010] |
 |
| |
11:00 |
Petition
of M/s Navlakha Translines for adjudication of dispute regarding
provision of non-discriminatory open access.
[Case No. 41 of 2010] |
 |
| |
12:00 |
Petition of M/s
JSW Energy (Ratnagiri) Ltd for adjudication of disputes arisen
between JSW Energy (Ratnagiri) and Maharashtra State Electricity
Distribution Co. Ltd.
[Case No. 99 of 2010] |
 |
| |
12:00 |
Petition of M/s
JSW Energy (Ratnagiri) Ltd for adjudication of disputes arisen
between JSW Energy (Ratnagiri) and Maharashtra State Electricity
Distribution Co. Ltd.
[Case No. 9 of 2011] |
 |
|
|
11:00 |
Application
filed by M/s Adani Power Maharashtra Ltd for amendment of the
Transmission Licence No. 2 of 2009 granted to it by the Maharashtra
Electricity Regulatory Commission.
Petition
for Amendment of Transmission License No.2 of 2009.
[Case No. 62 of 2010] |
 |
| |
12:30 |
Petition
of Maharashtra State Electricity Distribution Company Ltd.,
for initiating enquiry in respect of revocation/ suspension
of License of Mula Pravara Electric Co-op Society Ltd. (MPECS).
[Case No. 10 of 2007] |
 |
| |
12:30 |
Petition
of Mula Pravara Electric Co.op Society Ltd. for violation of
provisions relating to grant of Open Access.
[Case No. 46 of 2010] |
 |
| |
15:00 |
Petition
of MSPGCL in regards to Additional Employee Expenses for grant
of the ex-gratia to the employees of MSPGCL for the year 2009-10.
[Case No. 15 of 2011] |
 |
| |
15:30 |
Petition
of MSEDCL for relaxation from constitution of Consumer Grievance
Redressal Forum at newly created Zones at Jalgaon, Nanded and
Baramati.
[Case No. 65 of 2010] |
 |
|
|
11:00 |
Petition
of Maharashtra Veej Grahak Sanghatna for initiating penalized
action against MSEDCL's Officers for implementing excessive
load shedding on single phase & Separate Agricultural Pumps
electricity users, by violating the MERC's load shedding guidelines
and Methodology.
[Case No. 81 of 2010] |
 |
| |
12:30 |
Petition
of Maharashtra Airport Development Company Ltd, in the matter
of taking on Record the Distribution Licensee status of Maharashtra
Airport Development Company Ltd. for Multi Product Special Economic
Zone at Mihan, Nagpur.
[Case No. 16 of 2011] |
 |
| |
15:00 |
Petition
of Shri Ravindra Vinayak Jawlekar challenging the Notice issued
by MSETCL under Indian Telegraph Act, 1885 for erection of 400
KV Koradi-Wardha Line.
[Case No. 102 of 2010] |
 |
| |
16:00 |
Complaint
of M/s Godrej Properties & Investment Pvt Ltd under Section
142 r/w Section 149 of the Electricity Act, 2003, against MSEDCL
for non-compliance of Tariff Orders of MERC dated and / or applicable
from 10th March, 2004, 1st June 2008 and 1st August 2009.
[Case No. 18 of 2011] |
 |
|
|
11:00 |
Petition
of M/s Kay Power & Paper Ltd for grant of interim unit rate
for co-generation project.
[Case No. 89 of 2010] |
 |
| |
12:30 |
Petition
of MSEDCL for approval of deviations taken in Request for Proposal
and Power Purchase Agreement from Standard Bidding Documents
issued by Ministry of Power for procurement of 600 MW (±10%)
base load power on long term basis through tariff based Competitive
Bidding Process (Case I)
[Case No. 88 of 2010] |

to 18 March 2011 at 17:00
|
| |
15:00 |
Petition
of M/s Jain Irrigation Systems Limited seeking review of the
Commission's Order dated 17.08.2009 passed in Case No. 116 of
2008.
[Case No. 34 of 2010] |
 |
| |
16:00 |
PSmt.
Meena Kishinchand Tunya's Petition under Section 142 of the
EA, 2003, against MSEDCL for non-compliance of the CGRF order
dated 19.12.2008, passed by the CGRF, Kalyan.
[Case No. 27 of 2009] |
 |
| |
16:30 |
Petition
of Shyam Oil Mill for Non compliance of the Order dated 13.10.2010
passed by Hon'ble CGRF Amravati Zone, AKOLA in Case No. 59 of
2010.
[Case No. 106 of 2010] |
 |
| |
16:30 |
Petition
of Deepak Shankarlal Agrawal for Non Compliance of the Order
passed by the CGRF Amravati Zone, AKOLA in Case No. 57 of 2010,
Order dated 13th October, 2010.
[Case No. 107 of 2010] |
 |
| |
16:30 |
Petition
of Shivam Oil Industries for Non Compliance of the Order passed
by the CGRF Amravati Zone, AKOLA in Case No. 56 of 2010, Order
dated 12th October, 2010.
[Case No. 108 of 2010] |
 |
|
|
15:00 |
Petition
of Maharashtra Veej Grahak Sanghatna for initiating penalized
action against MSEDCL's Officers for implementing excessive
load shedding on single phase & Separate Agricultural Pumps
electricity users, by violating the MERC's load shedding guidelines
and Methodology.
[Case No. 81 of 2010] |
 |
|
|
11:00 |
Petition
in the matter of Distribution Licence of M/s Reliance Infrastructure
Ltd.
[Case No. 78 of 2010] |
 |
| |
16:00 |
Petition
of Rajesh Narnaware, in the matter of violation of Govt. Notification
dated 06/06/2005 and M.E.R.C. Order dated. 27/09/2006.
[Case No. 113 of 2010] |
 |
| |
17:00 |
Petition
of MSETCL for consideration of additional Employee Expenses
for grant of the ex-gratia to the employees of MSETCL for the
year 2009-10.
[Case No. 21 of 2011] |
 |
| |
17:30 |
Complaint
of M/s Pace Investment Pvt Ltd under Section 142 r/w Section
149 of the Electricity Act, 2003 for Non-Compliance of the Order
of Internal Grievance Redressal Cell, Pune dated 14.09.2010.
[Case No. 2 of 2011] |
 |
|
|
11:00 |
Petition
of The Tata Power Company Ltd, in the matter of seeking Approval
of the proposed Quantum of Power for Medium term power procurement
through Competitive bidding process under Case 1 bidding and
for the approval of Bidding documents in accordance with Section
63 of the Electricity Act 2003 "Guidelines for Competitive
Bidding for determination of tariff for procurement of power
by Distribution licensees", dated 19th January 2005 as
notified and amended by th Ministry of Power (MoP).
[Case No. 20 of 2011] |
 |
| |
12:30 |
Suo
Motu Hearing in the matter of Order dated 22nd February, 2010
in Case No. 60,81,83,84,85,86 of 2009 for seeking changeover
from BEST Undertaking to Tata Power Company Limited.
[Case No. 30 of 2011] |
 |
| |
14:30 |
Petition
of M/s Reliance Infrastructure Ltd for review of Order dated
27th January, 2011 in Case No. 53 of 2010.
[Case No. 17 of 2011] |
 |
| |
14:30 |
Petition
of Reliance Infrastructure Ltd for Adoption of Tariff determined
through transparent process of bidding under Section 63 of the
Electricity Act, 2003 in respect of Power Purchase Agreement
entered into between Reliance Infrastructure Limited on the
one hand and Vidharbha Industries Power Limited respectively.
[Case No. 12 of 2011] |
 |
| |
14:30 |
Petition
of Reliance Infrastructure Ltd for Adoption of Tariff determined
through transparent process of bidding under Section 63 of the
Electricity Act, 2003 in respect of Power Purchase Agreement
entered into between Reliance Infrastructure Limited on the
one hand and Chitrangi Power Private Limited.
[Case No. 13 of 2011] |
 |
| |
14:30 |
Petition
Wardha Power Co Ltd for adoption of Tariff and approval of Power
Purchase Agreement dated 04.06.2010 for 260 MWs of Power under
Section 63, 86 (1) (b) and 86 (1) (f) of the Electricity Act,
2003 pursuant to Case - 1 Bidding Procedure through Tariff Based
Competitive Bidding Process initiated by M/s. Reliance Infrastructure
Limited in terms of Request of Proposal for Medium Term issued
on 30.07.2009.
and
Dispute between a Generating Company and the Distribution Licensee
as a result of the deliberate and willful failure of the distribution
licensee to seek statutory adoption of the tariff and approval
of Power Purchase Agreement (PPA) within a reasonable timeframe
so as to enable supply of power from 01.04.2011 in terms of
the PPA dated 04.06.2011.
[Case No. 11 of 2011] |
 |
| |
14:30 |
Petition
of M/s Reliance Infrastructure Ltd for “in principle” approval
for Medium Term Power Procurement under the provisions of Section
86 (1) (b) of the Electricity Act, 2003 read with Regulation
24 of the Maharashtra Electricity Regulatory Commission (Terms
& Condition of Tariff) Regulations, 2005. Case No. 29 of 2011
[Case No. 29 of 2011] |
 |
|
|
11:00 |
Suggestions/
Objections on Maharashtra State Load Despatch Centre's (MSLDC)
Petition for approval of Budget for FY 2011-12 (Case No 90 of
2010).
[Case No. 90 of 2010] |
 |
| |
15:00 |
Petition
of Wardha Power Company Ltd for quashing of letter dated 30.03.2010
issued by the Maharashtra State Transmission Company Ltd., demanding
transmission charges.
[Case No. 29 of 2010] |
 |
| |
15:00 |
Petition
of Wardha Power Company Limited under Section 86 (1) (f) of
the Electricity Act, 2003 (read with Section 63 and 86 (1) (b))
seeking recovery of unpaid dues/ tariff for supply of electricity
in terms of Power Purchase Agreement dated 13.05.2009.
[Case No. 14 of 2011] |
 |
| |
16:00 |
Petition
for adoption of Tariff and approval of reduction in requisitioned
capacity to 1000 MW for Medium Term Power Procurement under
Case 1
Bidding.
[Case No. 23 of 2011] |
 |
| |
17:00 |
Petition
of MSEDCL for approval of deviations taken in Request for Proposal
and Power Purchase Agreement from Standard Bidding Documents
issued by Ministry of Power for procurement of 600 MW (±10%)
base load power on long term basis through tariff based Competitive
Bidding Process (Case I).
[Case No. 88 of 2010] |
 |
|
|
10:00 |
Petition
for adoption of Tariff and approval of reduction in requisitioned
capacity to 1000 MW for Medium Term Power Procurement under
Case 1
Bidding.
[Case No. 23 of 2011] |
 |
| |
11:00 |
Petition
Wardha Power Co Ltd for adoption of Tariff and approval of Power
Purchase Agreement dated 04.06.2010 for 260 MWs of Power under
Section 63, 86 (1) (b) and 86 (1) (f) of the Electricity Act,
2003 pursuant to Case - 1 Bidding Procedure through Tariff Based
Competitive Bidding Process initiated by M/s. Reliance Infrastructure
Limited in terms of Request of Proposal for Medium Term issued
on 30.07.2009
and
Dispute between a Generating Company and the Distribution Licensee
as a result of the deliberate and willful failure of the distribution
licensee to seek statutory adoption of the tariff and approval
of Power Purchase Agreement (PPA) within a reasonable timeframe
so as to enable supply of power from 01.04.2011 in terms of
the PPA dated 04.06.2011
[Case No. 11 of 2011] |
 |
| |
11:00 |
Petition
of Reliance Infrastructure Ltd for Adoption of Tariff determined
through transparent process of bidding under Section 63 of the
Electricity Act, 2003 in respect of Power Purchase Agreement
entered into between Reliance Infrastructure Limited on the
one hand and Vidharbha Industries Power Limited respectively.
[Case No. 12 of 2011] |
 |
| |
11:00 |
Petition
of Reliance Infrastructure Ltd for Adoption of Tariff determined
through transparent process of bidding under Section 63 of the
Electricity Act, 2003 in respect of Power Purchase Agreement
entered into between Reliance Infrastructure Limited on the
one hand and Chitrangi Power Private Limited.
[Case No. 13 of 2011] |
 |
| |
11:00 |
Petition
of M/s Reliance Infrastructure Ltd for review of Order dated
27th January, 2011 in Case No. 53 of 2010.
[Case No. 17 of 2011] |
 |
| |
11:00 |
Petition
of M/s Reliance Infrastructure Ltd for "in principle"
approval for Medium Term Power Procurement under the provisions
of Section 86 (1) (b) of the Electricity Act, 2003 read with
Regulation 24 of the Maharashtra Electricity Regulatory Commission
(Terms & Condition of Tariff) Regulations, 2005.
[Case No. 29 of 2011] |
 |
| |
11:00 |
Petition
of M/s Abhijeet MADC Nagpur Energy Pvt. Ltd. Section 63, Section
86 (1) (b) and Section 86 (1) (f) of the E.A. 2003
and
Power Purchase Agreement dated 04.08.2010 (PPA) between Abhijeet
MADC Nagpur Energy Private Limited And Reliance Infrastructure
Ltd.
and
Request for the adoption of Tariff and approval of Power Purchase
Agreement dated 04.08.2010 for 55 MW of Power under Sec 63 and
86 (1) (b) of the Electricity Act, 2003 pursuant to Case 1 Bidding
Procedure through Tariff Based Competitive Bidding Process initiated
by Reliance Infrastructure Limited in terms of Request for Proposal
for Medium Term issued on July 30, 2009.
and
Dispute between a generating Company and the distribution Licensee
as a result of the deliberate and willful failure to comply
with the terms and conditions of the PPA by Reliance Infrastructure
Limited.
and
Breach by the Respondent of the Order dated July 21, 2009 passed
by this Hon'ble Commission in Case No. 94/ 2008 whilst approving
the request for proposal pursuant to which the PPA was executed
[Case No. 42 of 2011] |
 |
| |
15:00 |
Petition
of Maharashtra Veej Grahak Sanghatna for initiating penalized
action against MSEDCL's Officers for implementing excessive
load shedding on single phase & Separate Agricultural Pumps
electricity users, by violating the MERC's load shedding guidelines
and Methodology.
[Case No. 81 of 2010] |
 |
|
|
11:00 |
Petition
of MSEDCL for Deferment of the implementation of MYT Regulations
2011.
[Case No. 24 of 2011] |
 |