MAHARASHTRA ELECTRICITY REGULATORY COMMISSION |
||||||||||||||||||
|
Guidelines For
In-Principle Clearance of Proposed Investment Schemes |
||||||||||||||||||
| I] | BACKGROUND | |||||||||||||||||
|
§
|
The
Electricity Act, 2003 has given State Electricity Regulatory Commissions
wide-ranging powers and flexibility to regulate the power sector.
|
|||||||||||||||||
|
§
|
Under
Section 61, the Commission has the power to specify the terms and conditions
for the determination of tariff and in doing so it is required to be guided
by the factors which would encourage competition, efficiency, economical
use of the resources, good performance and optimum investments so that
generation, transmission, distribution and supply of electricity is conducted
on commercial principles and the consumer’s interest is safeguarded. Under
the proviso to Regulation 4.1 of the Tariff Regulations, the need to link
tariff adjustments to increases in the productivity of capital employed
is also to be kept in view.
|
|||||||||||||||||
|
§
|
While
Capital Investment is required to be made by Licensees for various purposes
like the creation of new infrastructure to meet load growth, to meet statutory
requirements, to strengthen the existing system and increase its efficiency,
replace old/ obsolete assets, any such capital investment increases the
capital base and consequently the reasonable return thus affecting the
tariff to consumers. It is therefore necessary to ensure that such capital
investment schemes being proposed are necessary and justified, and do
not impose an unnecessary burden on consumers by way of tariff.
|
|||||||||||||||||
|
§
|
During the Tariff Determination processes undertaken so far, various objectors
raised the issue of the prudence of the capital investment being made
by Licensees.
|
|||||||||||||||||
|
§
|
After
examining all aspects in this regard, the Commission directed Licensees
Tata Power Company (TPC) and Reliance Energy Limited (REL) to submit details
in respect of all proposed Capital Investments exceeding Rs. 10 crores
for approval to the Commission.
|
|||||||||||||||||
|
§
|
For
evaluation of these and future proposals in respect of all Licencees,
the methodology and evaluation criteria are outlined below.
|
|||||||||||||||||
| II] |
|
OBJECTIVES | ||||||||||||||||
| The objectives are: | ||||||||||||||||||
|
§
|
To
lay down the approach and methodology for ex-ante assessment of major
investment schemes for considering in-principle clearance.
|
|||||||||||||||||
|
§
|
To spell-out the evaluation criteria for such ex-ante assessment. | |||||||||||||||||
|
§
|
To
lay down guidelines for the submission of Feasibility Reports so as to
facilitate easy evaluation and monitoring of such proposed investment
schemes against benchmark figures.
|
|||||||||||||||||
| III] |
|
METHODOLOGY | ||||||||||||||||
| The following is the methodology adopted by the Commission: | ||||||||||||||||||
|
A)
|
Submission of Three-Year Capital Investment Plan: | |||||||||||||||||
|
§
|
The
Licensees shall submit a 3-year Rolling Capital Investment Plan outlining
the major schemes proposed for each Financial Year. The capital investment
plans should be internally consistent and reconcilable with other relevant
proposals and supporting information presented in the submission such
as demand projections, network reliability and design criteria.
|
|||||||||||||||||
|
B)
|
Capital Investment Schemes : | |||||||||||||||||
|
§
|
For
the purpose of these guidelines, a Capital Investment Scheme means any
non-recurring capital expenditure programme for the acquisition, construction
or improvement of a permanent facility in a particular sector (i.e. Generation,
Transmission, Distribution, General, etc.) or a geographical region.
|
|||||||||||||||||
|
§
|
The
Scheme shall be planned considering a 3-5 year investment horizon for
Generation and transmission related investments, and a 1-3 year horizon
for Distribution-related investments.
|
|||||||||||||||||
|
§
|
The scope of investments included in each Scheme shall be any of the following: | |||||||||||||||||
|
(i)
|
Works of a similar or related nature | |||||||||||||||||
|
For
example: New Receiving Stations proposed at different locations within
the licence area must be clubbed together and presented as a Scheme for
New Receiving Stations, Schemes for modernization / augmentation of the
Transmission cables must be presented together, Information Technology
Schemes, SCADA and Communication Equipment at the region/State level,
Schemes for Major Replacement of Old Equipment etc.
|
||||||||||||||||||
|
(ii)
|
Different
types of Works within a geographical area, say in a District
For example, all capital investments covered under a District Integrated Scheme can be presented together as a Scheme. |
|||||||||||||||||
|
(iii)
|
An independent identifiable project as would be submitted to a financial institution like REC, PFC, etc or for funding under APDRP. | |||||||||||||||||
|
C)
|
Submission of Feasibility Reports (FRs): | |||||||||||||||||
|
§
|
For
those Capital Investment Schemes exceeding Rs. 10 crores, the Licensee
should submit Feasibility Reports for the Commission's In-Principle Approval
with a broad Cost-Benefit Analysis. These capital investment proposals
should constitute a least cost plan.
|
|||||||||||||||||
|
§
|
The
FRs must clearly outline the scope and objectives of the proposed Scheme
and explain how the Scheme meets the evaluation criteria mentioned herein.
|
|||||||||||||||||
|
§
|
The
FRs must be accompanied by such information, particulars and documents
to support the details contained in the plan including technical reports,
design criteria, supplier/contractor quotations, term sheets of financing
agencies etc., as may be required to enable assessment of the nature involved
in ex-ante, in-principle clearance.
|
|||||||||||||||||
|
§
|
The
Commission may, from time to time, also lay down formats for submission
of FRs so as to facilitate assessment and.
|
|||||||||||||||||
|
§
|
The FRs should address all the various aspects
of the Scheme as set out below. (The enclosed format is only the scrutiny
sheet the Commission would use for assessment of the Scheme with a view
to granting In-Principle Clearance.)
|
|||||||||||||||||
|
D)
|
Evaluation of the Feasibility Report: | |||||||||||||||||
|
§
|
The Commission plans to adopt a 2-Stage Approval Process. | |||||||||||||||||
|
§
|
In-Principle Clearance | |||||||||||||||||
|
§
|
Final Approval during the Tariff Determination Process and/or ARR Review | |||||||||||||||||
|
§
|
When submitting an application for In-Principle
Clearance of the proposed Capital Investment Scheme, the Licensee will
be expected to indicate clearly and separately (a) the Scope and (b)
the Objectives of the proposed Scheme. The application should cover
all the aspects mentioned in these guidelines and should explain how the
Scheme measures up to the evaluation criteria. In this stage, the Scheme
would be given clearance considering primarily its scope and objective,
while keeping in view the criteria.
|
|||||||||||||||||
|
§
|
During the Tariff Determination Process
and/or ARR Review, the following will be borne in mind when granting final
approval to the Scheme.
|
|||||||||||||||||
|
§
|
To what extent the scope and objectives
given at the time of In-Principle Clearance have been achieved.
|
|||||||||||||||||
|
§
|
What is the actual expenditure incurred
by the Licensee, as against the amount considered while granting In-Principle
Clearance with justification for significant variations, particularly
on the higher side.
|
|||||||||||||||||
|
§
|
Actual benefits and results achieved or to be achieved. | |||||||||||||||||
|
§
|
The Capital Investment Scheme Proposals
will be, inter alia, subjected to the following evaluation and filtering
mechanism:
|
|||||||||||||||||
| 1) | Statutory/Safety Requirement | |||||||||||||||||
| 2) | Need for the Investment | |||||||||||||||||
| a. | Demand Side Requirement | |||||||||||||||||
| b. | Technical Justification | |||||||||||||||||
| c. | Urgency | |||||||||||||||||
| d. | Prudence of the Investment | |||||||||||||||||
| 3) | Cost Assessment and Possibility of Phasing the Investment | |||||||||||||||||
| 4) | Benefits and Costs to Consumers | |||||||||||||||||
| 1) | Statutory / Safety Requirement | |||||||||||||||||
|
§
|
Is the investment necessary to discharge
the duties / obligations as per E.A. 2003 or to meet any other statutory
or safety requirement?
|
|||||||||||||||||
|
§
|
Is the investment likely to constitute or
result violation of any of the provisions of the E.A. 2003, and if so,
the safeguards.
|
|||||||||||||||||
| 2) | Need for the Investment | |||||||||||||||||
| a. | Demand Side Requirement (For T&D Schemes) | |||||||||||||||||
|
§
|
Whether equipments are operating close to
their rated capacities and capital investment is necessary -
|
|||||||||||||||||
| (a) | To reduce the load on the existing equipment to prolong the life of the equipment | |||||||||||||||||
| (b) | To increase the reliability of the system. | |||||||||||||||||
| (c) | To facilitate the creation of back-up facilities during scheduled maintenance operations. | |||||||||||||||||
|
§
|
Whether the capital investment is necessary
to set-up the infrastructure required to meet normal load growth or to
reach new Consumers
|
|||||||||||||||||
|
§
|
Whether the investment is necessary for
increasing administrative efficiency which in turn will result in better
services to the consumers.
|
|||||||||||||||||
|
§
|
Are the assets or facilities being created
multiple use assets which can be used in some other business, and to what
extent.
|
|||||||||||||||||
| b. | Technical Justification | |||||||||||||||||
|
§
|
Does the Scheme meet Design Criteria which
are in keeping with prevailing norms/standards
|
|||||||||||||||||
|
§
|
Whether Replacement of Old Equipment is
necessary for equipment which has outlived its normal life-span.
|
|||||||||||||||||
|
§
|
Is the Useful life of the equipment reasonable?
|
|||||||||||||||||
|
§
|
What is the average rate of technology obsolescence for that equipment? | |||||||||||||||||
|
§
|
Does the investment increase the efficiency
in Operations and Maintenance & improve reliability of Supply.
|
|||||||||||||||||
|
§
|
Whether the investment is necessary for
a reduction in the T&D Losses (for T&D Schemes)
|
|||||||||||||||||
| c. | Urgency | |||||||||||||||||
|
§
|
Whether the capacity planned is commensurate with demand growth | |||||||||||||||||
|
§
|
Is it possible to defer the investment for its optimization. | |||||||||||||||||
| d. | Prudence of the Investment | |||||||||||||||||
|
§
|
Whether other alternatives have been considered,
with brief details of the results, and the basis on which the proposed
alternative was selected.
|
|||||||||||||||||
|
§
|
Whether the investment results in duplication
of existing infrastructure (owned by any other Licensee, or that Licensee
itself)
|
|||||||||||||||||
|
§
|
Is the proposed investment a necessity for
the conduct of business, or is it a luxury, the burden of which is being
passed on to consumers.
|
|||||||||||||||||
| 3) | Cost Assessment and Possibility of Phasing the Investment | |||||||||||||||||
|
§
|
Whether Cost Estimates and likely escalations
are reasonable and in keeping with market rates
|
|||||||||||||||||
|
§
|
Whether Recurring Costs associated with the Scheme are reasonable | |||||||||||||||||
|
§
|
Whether the least cost option has been considered | |||||||||||||||||
|
§
|
What is the actual amount of expenditure,
if any, on the Scheme incurred to date by the Licensee
|
|||||||||||||||||
| 4) | Benefits to Consumers | |||||||||||||||||
|
§
|
What are the broad quantitative and qualitative benefits to consumers | |||||||||||||||||
|
§
|
Is the Return on Investment justifiable from the consumer's point of view | |||||||||||||||||
|
§
|
What is the likely net impact on consumers
over a 5-year period considering the recurring costs and broad Cost-Benefit
analysis.
|
|||||||||||||||||
|
§
|
What are the results / benefits observed so far, if applicable. | |||||||||||||||||
| IV] | Time Frame for Submission of FRs. | |||||||||||||||||
|
The Licensees are expected to submit a 3-year
rolling Capital Investment Plan along with the relevant FRs each year
by the end of the third quarter of the previous Financial Year (by the
end of the last Quarter of the current year in case of the next 3-year
period).
|
||||||||||||||||||
| These Guidelines issue with the approval of the Maharashtra Electricity Regulatory Commission. | ||||||||||||||||||
|
Sd/-
(A.M. Khan), Secretary, MERC. |
||||||||||||||||||
| Dated : 9th February, 2005. | ||||||||||||||||||
|
|
||||||||||||||||||
|
FORMAT
(for use by the Commission)
Illustrative Assessment of FRs for Transmission and Distribution Schemes. |
||||||||||||||||||
| I. | In-principle Clearance stage: | |||||||||||||||||
| A] | Particulars furnished in the Application | |||||||||||||||||
|
||||||||||||||||||
| B] | Particulars furnished in the Feasibility Report | |||||||||||||||||
|
||||||||||||||||||
|
||||||||||||||||||
| II. | During final approval stage similar formats will be used and comparison of final Vs original will be made. | |||||||||||||||||
|
|