Before the
13th floor, Centre No.1,
World Trade Centre, Cuffe Parade, Mumbai 400 005.
Tel. 22163964 / 22163965, Fax No.
22163976
E-mail mercindia@mercindia.com
Website: www.mercindia.com
In the matter
of Review of Order dated 1.7.2004
regarding determination of ARR and Tariff of M/s BSES Ltd. (now Reliance Energy
Limited)
Dr Pramod Deo, Member
Shri A. Velayutham,
Member
INTERIM ORDER
Dated: September 30, 2004.
After an
elaborate public process and following the provisions of law, the Commission
passed its detailed Order in respect of the electricity tariff of M/s BSES Ltd.
(now Reliance Energy Ltd. -- REL) for FY 2004-05, on July 1, 2004 in Case No.
18 of 2003. Thereafter, under affidavit dated August 4, 2004, REL sought review
of the Order on several counts. On the Commission’s direction, REL submitted a
further Petition on August 24, 2004, clarifying, in respect of each point
raised, as to how the Petition met the requirements of review under Regulation
85 (a) of the Commission’s Conduct of Business Regulations rather than being
the subject matter of appeal.
2.
At the outset, it would be useful to set out Regulation
85(a), which reads as follows:
“Any
person aggrieved by a direction, decision or order of the Commission, from
which (i) no appeal has been preferred or (ii) from which no appeal is allowed,
may, upon the discovery of new and important matter or evidence which, after
the exercise of due diligence, was not within his knowledge or could not be
produced by him at the time when the direction, decision or order was passed or
on account of some mistake or error apparent from the face of the record, or
for any other sufficient reasons, may apply for a review of such order, within
45 days of the date of the direction, decision or order, as the case may be, to
the Commission.“
3.
The Review Petition included, among other issues, a prayer
for redefining the LTP-2 category of REL at par with the definition of the
LTP-2 category determined in respect of the Tata Power Company (TPC). In the
meantime, the Commission also received representations from several LTP-2
consumers of REL (presumably with loads between 15 HP to 50 HP and belonging to
the earlier LTP-2 category) stating that their bills had risen very sharply and
they were faced with a tariff shock as a result of the tariff revision and
tariff rationalisation undertaken by the Commission. REL also submitted a
letter dated September 15, 2004 in this regard, seeking that the Commission
address this issue by revising the applicability of the two-part tariff to the
LT industrial consumers in line with MSEB’s tariff structure or, alternatively,
permit REL to defer the application of the new tariff until the next Tariff
Order. The Commission directed REL to submit a supplementary affidavit to
include this point fully in their Review Petition.
4.
The Petition was heard for admission on September 20, 2004.
Shri. Subodh Shah, Director, REL, made a presentation on the issues raised in
the Review Petition. With regard to the LTP-2 category, Shri Shah submitted
that, earlier, this category applied for consumers with loads between 15 HP to
50 HP. It was also a single-part tariff (i.e without fixed charges), and there
was no Power Factor (PF) penalty. The new LTP-2 category, however, covers
consumers from 15 HP upwards, and also introduces a two-part tariff along with
PF surcharge. As a result, the tariff of many consumers falling in this
category has risen very sharply in absolute terms. Shri Shah stated that REL
have around 12,000 consumers in the LTP 2 category, and in many cases their
bill amounts have increased by several times.
5.
With regard to the issues regarding the new LTP 2 tariff,
the Commission drew attention at the hearing to its consistent philosophy
applied in determining tariffs ever since its first Tariff Order for the
Maharashtra State Electricity Board (MSEB) in the year 2000, which includes
two- part tariff, PF penalty, reduction in the number of tariff slabs and
categories, introduction of contract demand, etc. The Commission expected REL
to educate their consumers regarding the philosophy and process of tariff
determination and the rationale for various changes. Since, unlike MSEB, REL's
tariff had been scrutinised and revised for the first time ever through the
regulatory dispensation, the rationalisation was bound to lead to some
difficulties. However, the
Commission decided that the Petition would be admitted only to the extent of
issues relating to LTP-2, considering that there appears to have been an
inadvertent tariff shock, which was inconsistent with the Commission's stated
philosophy. On this matter, therefore, the Commission was willing to consider
various solutions. The other matters essentially sought substantive
modifications unsupported by any such argument and were outside the limited
scope for review set out in Regulation 85, and could be agitated in appeal
which was not within the Commission’s jurisdiction. The Commission would
address them only to extent that any clarifications were necessary or relevant.
6.
As directed by the Commission, REL submitted an additional
affidavit on September 24, 2004, outlining three Options for modifying the
tariff applicable to the sub-category of 15 HP to 50 HP consumers within the
new LTP-2 category. REL elaborated on these Options at the second hearing held
on September 29, 2004.
7.
At this hearing, REL’s representatives submitted that they
had installed Maximum Demand (MD) meters for around 3,500 LTP-2 consumers, and
were in the process of doing so for the remaining consumers as per the schedule
laid down by the Commission in its Order. REL expected to achieve the metering
target by November-end. In the meantime, REL are continuing to charge those
LTP-2 consumers in respect of whom MD meters have not yet been installed, as
per the LTP-1 tariff, in accordance with the Order. REL added that the problem
of tariff shock had been realised where MD meters have been installed. REL had
intimated the concerned consumers to submit their desired Contract Demand. In
the meanwhile, REL had equated the Contract Demand to the Sanctioned Load for
billing purposes.
8.
Considering the urgent need to
mitigate the inadvertent tariff shock to this category of consumers and to
grant them immediate relief, the Commission has decided to address the issue of
the LTP 2 tariff through this Interim Order, and would deal with the remaining
issues raised by REL in its final Order on the Review Petition.
9.
Since REL’s tariff has been determined recently for the
first time through the regulatory process and under a new legal framework, the
Commission believes it is necessary to highlight certain aspects of the tariff
philosophy adopted by the Commission in its Tariff Orders for the MSEB and TPC,
and its approach while revising REL’s tariff. The REL Tariff Order dated July
1, 2004 states that:
“The Commission has determined the
tariffs applicable to BSES’ consumers, keeping in mind the existing tariff
structure of BSES, MSEB, BEST, the recently revised tariffs of TPC, and the
tariffs proposed by BSES, with the intention of reducing the imbalances between
the tariffs applicable for the same consumer category across Licensees in the
State.
The Commission has undertaken
significant rationalisation of categories and sub-categories/slabs as a result
of which the billing rate for some categories has increased, while that of some
others has been reduced, though both are subsidising categories. This is
inevitable in any tariff rationalisation exercise. The rationalisation has been
undertaken in such a way that the categories and slabs are similar to those of
the Maharashtra State Electricity Board (MSEB) and the Tata Power Company Ltd.
(TPC) to the extent possible.”
10.
The Commission has introduced a two-part tariff for HT
industrial consumers on the basis of Contract Demand, which is the cornerstone
for any kind of power system planning. The Commission had also introduced an
optional two-part tariff based on Contract Demand for MSEB’s LT
industrial/commercial consumers, who were also given the benefit of availing
Time of Day (ToD) tariff, depending on time of use of energy. For those MSEB
consumers having, historically, a tariff based on connected load, the
Commission could not fully do away with the HP-based tariff at one go. However,
it intends to do so in future once metering is completed. In respect of TPC,
since full MD-based metering is already in place, the Commission has not
specified any HP-based tariff. As far as REL are concerned, the Commission has
introduced a demand-based tariff and directed REL to complete MD metering for
its consumers by the end of December, 2004. The Commission would like to move
towards a LT-less distribution system for reducing distribution losses, which
are paid for by consumers.
11.
Another basic principle adopted by the Commission is that a
fixed charge based on Contract Demand/Billed Demand is more scientific than a
fixed charge based on connected load or per connection, which is often an area
of dispute between the licensee and the consumer. In respect of certain
categories, in the absence of adequate data, the Commission has been specifying
fixed charges on the basis of connected load or per connection. However, Contract
Demand or Sanctioned Load are the correct indicators of the load imposed by a
consumer and agreed to be delivered by the electricity supplier at any given
point in time. This also ensures that the consumer is charged for the facility
created to cater to his Contracted Demand or Sanctioned Load. The present
problem has arisen partly because the connected load of the affected consumers
(which has remained unchanged for a long time) has been directly equated with
the Contract Demand. This has been further aggravated due to the widely
fluctuating load usage pattern of such consumers in each month. Because of low
utilisation of Sanctioned Load, the concerned consumers end up paying a very
high bill, which was not intended by the Commission. This is particularly so in
the case of small industrial consumers in the REL area who are unaware of the
concept of Contract Demand and the need for optimising the demand requirement
to maintain a good load factor (i.e., more than 60%).
12.
The concept of Contract Demand has been prevalent for a
long time in the case of MSEB and TPC. The Commission directs REL to educate
their consumers regarding the concept of Contract Demand and the principles to
be borne in mind while deciding its level keeping in view factors such as the nature
of work, the tariff, and the penalty for exceeding it. The consumers, on their
part, should also seek to understand the concept and implications of Contract
Demand and the need to enter into an agreement with regard to Contract Demand.
It may be useful to set out the meanings of Sanctioned Load, Connected Load,
Load Factor, Contract Demand and Maximum Demand, which are broadly as follows:
“Sanctioned
Load” means load in kilowatt
(kW)/Horsepower (HP) mutually agreed between the Distribution Licensee and the
consumer; i.e. the load specified
in the agreement.
“Load
factor” means the ratio of total number
of units consumed during a given period to the total number of units which may
have been consumed had the contract demand/sanctioned load been maintained
throughout the same period, subject to availability of supply from the
Distribution Licensee and shall usually be expressed as a percentage;
“Contract
Demand” means demand in kilowatt
(kW)/kilovolt ampere (kVA), mutually agreed between the Distribution Licensee
and the consumer as entered into in the agreement;
“Maximum
Demand” in kilowatts or kilovolt amperes,
in relation to any period shall, unless otherwise provided in any general or
special order of the Commission, mean twice the largest number of kilowatt
hours (kWh) or kilovolt ampere hours (kVAh) supplied and taken during any
consecutive thirty minute blocks in that period.
In
the past, the Licensees used to levy tariff on the basis of “Connected load”,
which normally means the sum of rated
capacities of all the energy consuming devices on the consumer’s premises,
which can be operated simultaneously.
13.
The Connected Load will typically be higher than the
Contract Demand, as all the equipments are not used at the same time, resulting
in diversity of load operations. The consumers should have the freedom to
reduce their Contract Demand based on their actual requirements, after studying
their total load, load factor, and diversity factor rather than simply equating
the Connected Load to Contract Demand. Thus, consumers may opt for a level of
Contract Demand, which is less than their Connected or Sanctioned load, while
at the same time taking into account the penalty for exceeding Contract Demand.
14.
The Commission has considered but not adopted any of the
three Options put forward by REL with regard to LTP 2 keeping in view its
tariff philosophy. Instead, after careful consideration and in order to give
immediate relief to many affected consumers, and consistent with its stated
principles, the Commission has decided to modify the LTP 1 and LTP 2 tariff
categories as follows, all other stipulations remaining the same:
Tariff as per Order dated 1.7.2004
|
Revised Tariff w.e.f. 1.10.2004
|
||||
|
Category |
Fixed Charges |
Energy
Charges |
Category |
Fixed Charges |
Energy
Charges |
|
|
|
(paise/kWh) |
|
|
(paise/kWh) |
|
LTP-1 (0 to 15 HP) |
Rs.150
per month |
400 |
LTP-1 (0 to 50 HP) |
Rs.150
per month |
400 |
|
LTP-2 (above
15 HP) |
Rs.374
per kVA |
300 |
LTP-2 (above 50 HP) |
Rs.374 per kVA |
300 |
15.
The revised tariff has the advantage of being easy to
implement as well as bringing about greater similarity in the tariffs of REL
and TPC, since TPC’s LT-1 category (Commercial and non-Commercial supply having
Contract Demand less than 100 kVA) has the same tariff.
16.
The revised tariff as above will
be applicable from October 1, 2004, for the electricity consumption recorded
from that date onwards.
17.
At the hearing on September 29, 2004, REL agreed that the
effect of this tariff revision could be taken up through the truing up process
at the time of filing of the next Tariff Petition. In order to assess the
present implications of this modification in tariff, REL are directed to submit
the following data to the Commission within 2 weeks:
|
S.No. |
Parameter |
Consumer Category |
FY 03 |
FY 04 |
FY 05 |
|
|
|
|
|
|
|
Apr-June |
July-Aug |
|
1 |
Consumption |
LTP-I |
|
|
|
|
|
LTP-2 |
|
|
|
|
||
|
LTP-3 |
|
|
|
|
||
|
2. |
Connected Load (in kW) |
LTP-1 |
|
|
|
|
|
LTP-2 |
|
|
|
|
||
|
LTP-3 |
|
|
|
|
||
|
3 |
Sanctioned Load (in kW) |
LTP-1 |
|
|
|
|
|
LTP-2 |
|
|
|
|
||
|
LTP-3 |
|
|
|
|
||
|
4 |
Contract Demand (in kVA) |
LTP-1 |
|
|
|
|
|
LTP-2 |
|
|
|
|
||
|
LTP-3 |
|
|
|
|
||
|
5 |
Revenue (in Rs. Crore) |
LTP-1 |
|
|
|
|
|
Fixed
Charges |
|
|
|
|
||
|
Energy
Charges |
|
|
|
|
||
|
LTP-2 |
|
|
|
|
||
|
Fixed
Charges |
|
|
|
|
||
|
Energy
Charges |
|
|
|
|
||
|
LTP-3 |
|
|
|
|
||
|
Fixed
Charges |
||||||