Before
the
13th
floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005.
Tel.
22163964 / 22163965, Fax No. 22163976
E-mail
mercindia@mercindia.com
Website:
www.mercindia.com
In
the matter of
wrongful
application of HTP-II tariff for electricity supply to Maharashtra State
Farming Corporation, and related matters.
Dr
Pramod Deo, Member
Dated: August 19, 2003
M/s Maharashtra State Farming Corp. Ltd. (MSFC), Pune’s Petition
dated 25.10.2002 challenges the “illegal and arbitrary action of the
Respondent (MSEB) in issuing electricity bills on the basis of HTP-II instead
of HTP-VI or VII.” MSFC’s
substantive prayers are that:
i)
MSEB should consider the Petitioner as HTP-VI
or HTP-VII category for the purpose of billing instead of HTP-II (industrial
category) as is being done presently.
ii)
the bills (based on HTP-II tariff) raised by
MSEB be declared invalid, and refunds made for the period August 1998 to
September 2000. The bills for the period from 1979 onwards (since the HP based
agricultural tariff was introduced) should be corrected on the same lines.
iii)
MSEB should furnish records and proceedings
pertaining to the notice of Demand dated 5.8.2002 and 23.8.2002 for recovery of
arrears and disconnection in the event of failure on the part of the
Petitioner.
iv)
MSEB be restrained from recovering delayed
payment charges and interest on outstanding dues based on bills prepared on the
basis of faulty application of tariff category.
v)
all the outstanding bills revised on the basis
of HTP-VI & HTP-VII for settlement of arrears.
vi)
MSEB be directed to supply electricity through
its own network, and take over MSFC's existing network at its Walchandnagar
farms.
2. The hearing on 20th
November 2002 was adjourned at the request of Counsel for MSEB to facilitate a
field inspection of load and verification of the data to co-relate it with the
parawise remarks that could be submitted only on 18th November. The Petition was heard further on 10.1.2003
when Shri K.A. Durve, Counsel for MSFC set out the background of the case. MSFC are a Government of Maharashtra (GoM)
undertaking registered under the Companies Act 1956 and came into existence in
1963 under the provisions of the Maharashtra Agricultural Lands (MAL) (Ceiling
on Holdings) Act, 1961. Thereafter,
under Section 28 of the MAL Act, the surplus land belonging to Walchandnagar
Industries, Walchandnagar, District Pune was taken over by GoM and handed over
to MSFC with the existing infrastructure, including electricity network, roads,
residential quarters, etc., for the purpose of management and cultivation. Counsel for MSFC submitted that their entire
activity is `agricultural’ and not `industrial’ or `commercial’ as per their
Articles of Association.
3. MSFC Counsel
referred to Section 21 of the MAL Act, which stipulates that, after the
acquisition of land, the activity (i.e. of producing raw material for the
manufacture of any goods, articles or commodity by the undertaking) is to be
maintained in respect of the acquired land. At that time, the contention of the
GoM was that, when the rights were taken over by them, the status of raw
material would not be affected and, therefore, this special provision was
incorporated in the Act.
4. Counsel for MSFC
stated that upto 1979 MSEB were supplying electricity on a metered basis to
Walchandnagar Industries who, in turn, used to supply it to their constituent
units. In 1979, MSFC set up a separate transformer (22 / 6.6 KV, 500 kVA) at
their own cost at Kalamb for drawing energy for mixed purposes viz. (i)
agriculture (ii) their divisional offices, and (iii) domestic use of their
employees. MSFC were drawing power at a
single point, and MSEB were charging them on the basis of metered consumption
at the industrial tariff HTP-II. Till 1987, as a general practice, bills were
issued on the basis of actual meter reading. Thereafter, the HP based tariff
for agricultural pump sets was introduced, but it was not extended to MSFC, who
have a mixed load that is predominantly agricultural. Counsel submitted that, while their end-use requirement is only
for 440 volts, MSFC were receiving power for their distribution network at 6.6
KV, which therefore requires further stepping down. This compelled MSFC to install a large number of additional
transformers at various places. Drawing the Commission’s attention to para 6 of
the Petition, Counsel pointed out that MSFC had requested MSEB on various
occasions to supply at 440 volts through the MSEB’s own network, but to no
avail.
5. To a query from the
Commission, Counsel for MSFC clarified that, apart from small garages for repairing
their own vehicles/ tractors, etc., administrative offices and flour mills for
the employees, no industrial or commercial activities were carried out. As stated in the Petition, Counsel submitted
that, in 1991, MSFC requested MSEB that the electricity consumption for their
agricultural farms and electric pumps installed at various wells be charged as
per the HP (agricultural) tariff.
Similarly, in 1993, MSEB were asked to segregate residential connections
and charge on the basis of metered residential consumption. Neither request was acceded to, and MSEB continued charging MSFC on the very
much higher basis of the HTP-II (Industrial) tariff. The matter was followed up
at various levels with the MSEB and GoM, without result.
6. Referring to Para 9
of the Petition, MSFC Counsel submitted that MSEB's own officers, viz. the
Executive Engineer, Baramati, had recommended, based on a field survey, the
revision of tariff category to HTP-VII, but MSEB are now seeking to disown this
stand. In terms of the 1998 tariff,
most of MSFC's activities fall in the HTP-VII tariff category. He submitted
further that, subsequent to several communications while discussions on the
matter were in progress at different levels, MSEB issued a supplementary bill
amounting to Rs. 66,72,792/- on 4th March 2000. Thereafter, MSEB
served a disconnection notice vide telegram dated 23rd March 2000,
which MSFC replied to vide telegram dated 27th March 2000 citing the
dispute persisting. MSEB confirmed vide
their letter dated 10th April 2000 regarding the matter being under
consideration and referred to CE (Commercial), MSEB.
7. Owing to the delay
by MSEB with respect to changing the category of tariff applicable to them, the
MSFC Chairman, who is also the State Revenue Minister, was approached and a
meeting was held with him on 12th October, 2000. According to MSFC
Counsel, at this meeting MSEB officials agreed to the following, as summarized
at para 18 of the Petition:
i)
That for the month of October, 2000 and
thereafter, the assessment of bills would be made on the basis of Horse Power
(Block Tariff) or as per the Tariff mentioned in paragraph 3 of the minutes of
the meeting (annexed as EXHIBIT-G of the Petition),
ii)
That MSEB should issue appropriate orders for
change in tariff within 8 days,
iii)
That, if required, an Agreement be entered
into accordingly and immediately,
iv)
That the arrears (for the period from 1979 to
August 2000) be decided by MSEB in the meeting of their Board and, after
appropriating the amounts found due, the balance be returned to MSFC (this was
on account of the fact that MSFC had been wrongly forced to pay industrial
tariff when in fact the agricultural tariff ought to have been applied),
v)
That the meter readings and the demand charges
on the pending bills be revised and the amounts due be informed to MSFC for
expeditious payment.
8. However, it was
submitted on MSFC's behalf that MSEB called upon them to pay Rs. 29.50 lakhs,
said to have been worked out on the basis of the HTP-VII tariff for the period
from August 1998 to September 2000 on a provisional basis till final settlement
of the matter. The correctness of computation of this provisional bill was
questioned, the correspondence relating to which is at Exhibits- H, I, J, K and
L of the Petition. Meanwhile, MSFC
arranged to pay, in two phases till February 2001, an ad-hoc amount of Rs 15
lakhs. However, MSEB, took no final
decision. MSFC Counsel submitted that, thereafter the bills for the months of
October 2000 to June 2002 were raised from time to time with corrections on the
face of the bills applying HTP-VII tariff. But the arrears amount shown was
disputed and hence not paid by MSFC.
On 5th September, a bill for August 2002 without such tariff
category correction was issued to MSFC, the due date for payment being
21.9.2002.
9. MSFC were served
with a notice-dated 5.8.2002 for disconnection for non-payment of arrears
referred to in the bill for the month of June 2002, under Section 24 of the
Indian Electricity Act. MSFC
immediately took this up with the concerned authorities. However, the electricity supply was
disconnected on 14.8.2002. Counsel for
MSFC submitted that, during this whole sequence, MSEB never clarified the basis of their calculations for issue of
supplementary bill showing them to be in arrears even though MSFC were
regularly meeting their bill payment liabilities.
10. Counsel for MSFC
stated that, aggrieved by the disconnection, MSFC approached the High Court
in WP No.5141 of 2002 in
September 2002. Under its Order dated
13.9.2002, the Court directed that (i) MSFC should deposit Rs.14.50 lakhs
within 4 weeks and pay the current bills, (ii) MSFC should approach the
Commission within four weeks (subsequently extended) for the determination of
tariff applicable to their farms, and also directed MSEB to restore electricity
supply. MSFC have approached the
Commission accordingly.
11. In the light of the
above, Counsel summarized MSFC's contentions and prayers as follows:
·
MSFC's activities are `agricultural’ and,
therefore, the agricultural tariff should be made applicable to them.
·
MSEB should be restrained from charging
interest on the outstanding arrears, which are disputable, till final Orders on
the present Petition.
·
MSEB should give details of the computation on
the basis of which such 'arrears' were arrived at.
·
MSEB should take over the entire distribution
system from MSFC at mutually agreeable terms and start supplying electricity
directly to the individual consumers.
12. Counsel for MSEB contended that MSFC's
activities and consumption of electricity include agricultural, commercial,
industrial, residential purposes, etc., and that the tariff under the HTP-II
category has been correctly applied since MSFC are served at HT level. He submitted that, for MSFC’s benefit and
taking into consideration the peculiarities of their internal set up, MSEB have
bifurcated the entire connected load demand into two parts, i.e. 60% for the
agricultural activities and 40% towards residential / commercial activities,
and have been raising bills accordingly.
He pointed out that MSFC could have approached the Commission at the
time of the tariff revision process for a separate category for them to resolve
these problems, but did not do so.
Counsel further submitted that MSEB are prepared to make separate
metered supply points to individual consumers subject to compliance of all the
formalities and payment of the required amount by MSFC.
13. Clarifying
to the Commission the procedure MSEB had adopted while taking over other
distribution systems Counsel submitted that, in such cases, they had taken
over the entire distribution network along with individual consumers. However, in this particular case, the
consumer is only one, viz. MSFC.
Moreover, MSFC's distribution network is not compatible with the present
pattern of distribution infrastructure of MSEB. Thus, MSEB would have to create a separate distribution system
for the existing network for agriculture and a new network for residential
purposes, which would cost around Rs.50 lakhs.
However, if MSFC are prepared to contribute to the cost of installation
of the required distribution network, the matter could be considered by MSEB.
14. Regarding disconnection of power supply,
MSEB Counsel submitted that MSFC were a defaulter (even for the provisional
amount) and, in compliance of the High Court (Nagpur Bench) directives, MSEB
had issued disconnection notices for non-payment of arrears. Counsel admitted
that the case of MSFC, taking into account the nature of its activities and
manner of electricity supply and distribution, is a peculiar one and a lasting
solution acceptable to both parties needs to be arrived at.
15. In reply, Counsel for MSFC submitted that
MSEB can take-over the entire distribution network free of cost since MSFC lack
the required infrastructure for operation and maintenance of the system. Moreover, electricity distribution is not a
part of their functions. MSFC are also
ready to extend all help, including the possibility of financial support that
would have to be explored through budgetary support from the State Govt.
16. In further written
submissions furnished under their letter dated 13.12.2002, MSEB have stated
that the electricity supplied by MSEB to MSFC's transformer sub-station at
Kalamb (via a 22 KV line from the Walchandnagar sub-station) is further
distributed by the latter through 19 transformers to their constituents for
different purposes, and it is not possible to segregate and compute the quantum
of consumption for these different purposes at the respective locations since
MSEB have not provided the metering systems.
Meters have been installed by MSFC for their internal purposes without
reference to MSEB, and MSEB cannot testify to their correctness. Moreover, MSFC have not set up independent
networks separately for residential, commercial, industrial and agricultural
uses. Thus, MSEB contend that it is not
possible for them to compute the energy consumed for different purposes by
MSFC. In any case, as far as MSEB are
concerned, they supply electricity to MSFC at one point, the applicable tariff
category for which is HTP-II. MSEB have
argued that there is no other provision in the tariff approved by the
Commission for breaking up the charges into commercial, industrial, residential
and other uses where a consolidated supply is made at one point to a
consumer. As far as recommendations
made by MSEB officers is concerned, these are only their views, and the Board
has taken a decision in the matter.
17. Pursuant to
discussions at the initial admissibility hearing, a joint inspection was
carried out on 25.11.02, the report of which was furnished along with MSEB's
written submissions dated 13.12.02, setting out the locations of MSFC's
transformers, their capacity, distances, and the residential, commercial,
industrial and agricultural load connected to each. On the basis of the joint inspection, MSEB have submitted that,
out of the total connected load of 400 KW, 317 HP (237.75 KW) relates to
agricultural load, i.e. around 60%.
They have argued, however, that "there is no co-relation between
the quantum of load vis-à-vis consumption and the purpose-wise consumption
pattern can be altogether different than the pattern of load". MSEB have also pointed out that the
connected load (400 KW) is in excess of MSFC's sanctioned load (307 KW).
18. In their rejoinder
dated 3.1.2003, MSFC have pointed out, with supporting material, that MSEB have
in fact given separate connections to MSFC at some of their irrigation wells,
which are being charged at the agricultural tariff on HP basis. Similarly, MSEB have given residential
connections for some of MSFC's employees, installed separate meters, and are
recovering charges directly from them. In
fact, MSFC had been seeking installation of separate meters generally, but without
result. MSFC have also submitted that
the particulars of the provisional bill of Rs 29.50 lakhs provided by MSEB
clearly indicate that they are able to compute the loads consumed for different
purposes.
19. The basic issue in
dispute in this case concerns the tariff which should apply in the peculiar
circumstances of MSFC's operations at their erstwhile Walchandnagar farms. In the ordinary course, the Commission would
have jurisdiction to entertain the matter pertaining only to the period after
its coming into existence on August 12, 1999.
However, in the light of the High Court direction to the Commission in
the Mahad Manufacturers' Association case (Writ Petition No. 2286 of 1998) to
examine and report on a tariff hike effective from a date prior to the coming
into existence of the Commission, the Commission would have jurisdiction to
determine the matter only from the period from September, 1998 (i.e., with
reference to the MSEB tariff schedule effective from 1.9.1998) onwards, though
the parties would also be free to consider the principles of such determination
in the case of any negotiated settlement for the prior peroid.
20. The joint inspection
report dated 25th November 2002, furnished to the Commission on 13th
December 2002 in the course of these proceedings, which was carried out by MSEB
and MSFC, should be the basis for determination of the applicable tariff. From its first Tariff Order of May, 2000 in
Case No. 1 of 1999 onwards, the Commission has stressed the need for metered
billing. In the case of MSFC, since the
input energy is metered, a proportionate allocation of load based on the joint
inspection report is possible. In case
of mixed load on a particular distribution transformer, the metered load should
be the basis for billing.
21. Therefore, in view of
the above and in the circumstances of the case, the Commission passes the
following directions:
i)
MSEB shall recompute the supplementary bill
dated 4th March 2000 pertaining to the period from October 1998
onwards, based on the criteria set out at para 20 above. After appropriating the amounts found due
against the provisional or other payments already made by the Petitioner, the
balance should be claimed or returned, as the case may be, from /to MSFC, with
12% simple interest, taking the benchmark set for such interest in the
Commission’s tariff Order dated 5.5.2000.
The interest computation should be carried out for the period for which
it is due to MSEB or eligible for refund to MSFC. MSFC shall extend all co-operation towards speedy reconciliation
wherever required. The parties should
separately take appropriate steps in the light of this Order before the
concerned Bench of the High Court seized with the matter of arrears of MSEB dues,
if required in terms of those proceedings.
ii)
Similarly, bills for the subsequent period
should be recomputed on the same principles as above, and at rates as per the
approved tariff prevailing at the relevant time.
iii)
As far as billing for future periods is
concerned, a similar approach based on the above principles and on metered
billing should be adopted. However,
MSFC are also free to agitate their claims with regard to the tariff that
should apply to them in the course of the separate proceedings that have been
initiated for determination of MSEB’s tariff for 2003-04.
iv)
As far as billing disputes pertaining to the
period before October 1998 are concerned, the Commission, as explained earlier,
would not like to deal with them.
v)
Regarding take over of MSFC’s distribution
infrastructure, this is a matter best left to the commercial prudence and
negotiations between the parties.
| Sd/- | Sd/- | Sd/- | |
| (Jayant Deo) | (Dr Pramod Deo) | (P. Subrahmanyam) |
|
| Member | Member | Chairman, MERC |
|
Sd/- |
|||
| (A.M. Khan) | |||
| Secretary, MERC | |||
|
|||