Before
the
13th
floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005.
Tel.
22163964 / 22163965, Fax No. 22163976
E-mail
mercindia@mercindia.org.in
Website:
www.mercindia.org.in
In the matter of Review of Order dated 11.6.2004 regarding determination of ARR
and Tariff of Tata Power Company Ltd.
Shri
P. Subrahmanyam, Chairman
Dr
Pramod Deo, Member
Shri A. Velayutham
ORDER
Dated: 17th September, 2004.
After an
elaborate public process, the Commission passed its detailed Tariff Order in
the matter of Determination of Annual Revenue Requirement and Tariff applicable
to consumers of M/s Tata Power Company Ltd. (TPC) for FY 2003-04 and 2004-05
on 11th June, 2004 in Case
No. 30 of 2003. Thereafter, under affidavit dated 8th July, 2004, TPC purported
to seek certain clarifications on the Order.
However, TPC were directed to segregate the issues on which
clarifications were sought and those which were sought to be reviewed, and to
pursue the latter through a separate Petition if desired, indicating how each
issue met the requirements of the MERC (Conduct of Business) Regulations, 2004
governing review. Accordingly, TPC have
submitted the present Petition dated 26th July, 2004 seeking review
of the Tariff Order dated 11th
June, 2004. As directed by the Commission at the hearing held on 23rd
August, 2004, TPC also filed a further affidavit dated 27th August,
2004 elaborating on certain issues.
2. At the outset, it would be useful to set
out Regulation 85(a), cited in the Review Petition, which reads as follows:
“Any person
aggrieved by a direction, decision or order of the Commission, from which (i)
no appeal has been preferred or (ii) from which no appeal is allowed, may, upon
the discovery of new and important matter or evidence which, after the exercise
of due diligence, was not within his knowledge or could not be produced by him
at the time when the direction, decision or order was passed or on account of
some mistake or error apparent from the face of the record, or for any other
sufficient reasons, may apply for a review of such order, within 45 days of the
date of the direction, decision or order, as the case may be, to the
Commission.“
In
support of the plea for review, the Petition also cites Regulations 92 and 93
(which refer to the Commission’s inherent powers), 95 and 96 (which deal with the
Commission’s general powers to amend or rectify any defect or error in any
Order for the purpose of determining the real question or issue arising, and to
remove difficulties in giving effect to any provision of the Regulations).
3. The Petition was heard for admission on
23rd August, 2004. At the outset, Shri Janak Dwarkadas, Counsel for
TPC, submitted that the Review Petition raised various operational, commercial
and financial issues, but that TPC would not be pressing the last issue
relating to distribution franchisees.
The Commission observed that TPC had already approached the High Court,
and should not approach the Commission on matters that are only within the
ambit of appeal in the guise of a review.
For the substantive matters, which otherwise would not satisfy the
requirements under the Regulations governing review, alternative remedies are
available. The Commission was open to
providing any clarifications that might be required on relevant issues separately.
TPC Counsel submitted that, while clarifications had been asked for separately,
the present matters were not amenable to mere clarification.
Operational
Issues
(1) Shutting
down Unit 4
4. The Petition states that the
Commission’s directives to stop the operations of TPC’s Trombay Unit 4, except
during outage of Units 5 and 6, saves fuel expenses to a certain extent, and
that TPC had already been doing so whenever demand is slack. However, Unit 4 needs to be available for
about 150 days during the year, including the time when Reliance Energy Ltd.
(REL)’s unit is out, and should generate 500 MUs which cannot be produced by
Units 5 and 6 because of demand
variations. The Commission had allowed
purchase of only 61 MUs based on the monthly energy requirement. However, if the requirement is calculated on
hourly MW basis, this purchase quantum is not sufficient if Unit 4 is not
available. Therefore, TPC have asked
the Commission to reconsider the restriction on generation of Unit 4 to 112 MUs
.
5. TPC have further stated that Unit 4
provides generation support to the TPC system during peak hours. In the absence of Unit 4, if the Maharashtra
State Electricity Board (MSEB) system collapses during peak hours, the
islanding system may not be effective in arresting the collapse of the TPC grid
in Mumbai. According to TPC, the
Commission’s stipulation that only upto 61 MU may be purchased from MSEB, and
that TPC should not carry out any load shedding inspite of shutting down of
Unit 4 is not practicable since MSEB may not be able to supply during peak
hours when they are already carrying out load shedding of about 2000 MW daily
throughout the State. In this regard, TPC have referred to a recent
communication from MSEB asking them to reduce drawal and bring Unit 4 back
online. The Petition further states
that the cost of additional generation as a result of TPC’s proposal would be
only around Rs.10 crores, and the fuel cost would be 0.61% of the total fuel
cost. This is insignificant compared to
the risk to reliability and stability of the TPC grid and deprivation of MSEB
consumers during peak hours.
6. TPC have stated that Unit 4 requires
around 48 hours to attain full load, which would be problematic during
emergency periods. Moreover, since the
energy balance is reworked by the Commission by shutting down Unit 4 and
correspondingly increasing allocation of the balance units, an error has
occurred in the estimation of power purchase. TPC have cited the provisions
regarding error or mistake apparent on the face of the record in Regulation 85(a), and also Regulations 92, 93, 95 and 96 of
the Conduct of Business Regulations to support the maintainability of the
Petition on this point.
7. At the hearing, TPC Counsel submitted
that the matter of shutdown of Unit 4 had not been posed during the tariff
determination proceedings, and hence TPC had no opportunity to raise the issue,
which they would have done had they known that such a direction was being
contemplated. He pointed out that the
additional fuel cost amounts to less than 1%, but left the matter for the Commission to decide.
(2) Merit Order Dispatch
8. Referring to the
Merit Order stack considering backing down limits in the Table at page 113 of
the Order, the Petition details the implications of the oil support required
for Unit 5. Hence, it argues that the
additional oil requirement at this level of loading should be permitted for
calculation of variable cost. The plea
for review is supported citing the provision in Regulation 85(a) regarding the
discovery of new and important matter or evidence. At the hearing, Counsel for
TPC submitted that, with reference to the Table at page 110 of the Tariff
Order, the Commission itself had recognised that Unit 4 cannot be operated
below 150 MW due to technical limitations.
Similarly, Unit 5, which is the only coal fired Unit, would require oil
support if it is operated below 200 MW. That has not been provided for in the
Tariff Order, and thus justified review.
(3) Heat Rate
9. With regard to the
heat rate of Unit 5, the Petition states that the rate of 2447 Kcal/kWh
considered by the Commission for FY 2005 is based on TPC’s assumption that
minor fuels would be accounted separately, but the Commission had disallowed
that expenditure. In these circumstances,
the heat rate for fuel cost calculations should be 2469 Kcal/kWh, based on the
actuals for FY 2004 accepted by the Commission. At the hearing, TPC Counsel
submitted that this correction, being an error apparent on the face of the
record, requires to be made.
10. To a query of the Commission regarding the tenability of
review of such matters under the Regulations, TPC Counsel submitted that, in a
tariff determination process of such scale and complexity, there are bound to
be deficiencies and the exercise may be required to be fine-tuned when
anomalies are noticed. With regard to the Petition filed by TPC in the High
Court, Counsel conceded that appeal lay with the Appellate Tribunal under the
Electricity Act (EA), 2003, but it has yet to be constituted. As a result, TPC had to file a Writ in the
High Court. However, the issues raised
cannot really be dealt with in a Writ Petition, being matters of technical
detail. He reiterated that there are
errors apparent on the face of record, and some points may have been overlooked.
11. The Commission observed that the issues
raised by TPC are substantive in nature, and fundamentally question the very
basis of the tariff setting exercise and the determination based on detailed
analysis and application of Merit Order principles. It also essentially
challenges the considered judgement call of the Commission on various matters
on which there might be differing opinions or assessments, and would thus not
fall under the ambit of review.
12. As
regards TPC’s reference to higher purchase from MSEB being required in case of
shut down of Unit 4, and its linkage with grid stability under emergency
conditions, reiterated by Shri J.D. Kulkarni of TPC at the hearing, the
Commission notes that it has not restricted the source of power purchase to
only MSEB. In fact, at various places, the Tariff Order clearly states the
following:
·
“The Commission directs TPC to enter into an alternative
arrangement to purchase power during peak hours so as to ensure that load
shedding is not required.”
·
“The Commission may consider permitting additional cost of
purchase of power during peak hours for meeting energy requirement of License
Area operations arising of shutdown of Unit 4, through the FAC mechanism, based
on evidence submitted by TPC to substantiate its claims.”
·
“It would be economical to buy part of quantity at higher
rate rather than operating Unit 4 as a base load Station.”
·
“TPC may explore the option of selling electricity
generated using Unit 4 to MSEB and other States, in such a manner that there is
no additional burden on consumers of the License Area.”
At page 112 of the Tariff Order, the Commission has also
noted that:
“the approval of Ministry of Power for
installation of a second 500 MW set Unit No. 6 at Trombay Thermal Power Station
states that ‘the proposed Unit has been approved in replacement of Units 1 to 4
(3 X 62.5MW + 1 X 150 MW). As soon as the proposed Unit (6th Unit)
comes into operation, the existing three units amounting to 187.5 MW capacity
would be scrapped without fail. The fourth Unit of 150 MW capacity would be
relegated to standby duty and operated to meet peaking requirements only when
surplus gas is available for its operation.”
In view of the above, the Commission concludes that the
Operational Issues set out in the Petition do not meet the test of the
provisions governing review, and some of TPC’s concerns have already been
addressed in the Order itself. It may
also be mentioned in passing that MSEB’s letter of end June, 2004 regarding
drawal from Unit 4 (referred to by TPC at para 5 above) was addressed at a
particular time of unusual delay in the
onset of the monsoon rains.
(1) Demand
Charges for 220 kV off-take by REL
13. Citing the Commission’s observation in
its Tariff Order that the 220 KV interconnection at Borivli is only for standby supply and not for regular
drawal, and that REL should refrain from drawing normal power from this
interconnection, TPC’s Petition states that, instead, this interconnection is
being regularly used by REL for normal energy drawal, and that they have
written to the Commission earlier pointing this out. The demand in June, 2004 was 188 MVA, i.e. 34% of the demand at
the 22/33 KV supply point, which amounts to Rs.6.4 crores at the rate of Rs.340
per kVA. The Petition, therefore, seeks
that demand charges be fixed for 220
KVA supply to REL in line with the charges for the 22/33 KV supply point, which
would be treated and billed separately from the standby charges applicable from
1.6.2004. TPC have cited the clause in
Regulation 85, regarding discovery of an important matter or evidence, in
support of review.
14. The Commission notes that this issue is
contingent upon the disputes between TPC and REL pending before the Commission in
Case Nos. 3 and 4 of 2003, which have also been mentioned in the Tariff Order.
Accordingly, it would be resolved through the Commission’s forthcoming Orders
in those cases, and cannot be decided through review of the Tariff Order at
this stage.
(2) Demand
Charges for REL
15. The Petition states that, according to
Appendix 7 of the Tariff Order, the revenue from demand charges from REL 22/33
KV supply would be Rs. 274.44 crores,
computed on the basis of average monthly billing demand of 673 MVA. At pages 85-86 of the Tariff Order, billing
demand for FY 2005 has been projected to remain at the FY 2004 level. The average level of FY 2004 has been
derived from Annexure 1 of the additional information that had been submitted
by TPC vide letter dated 23rd April, 2004. In that submission, the billing demand for November, 2003 was
erroneously mentioned as 1807 MVA instead of actual demand of 602.5 MVA. The Petition points out that the revenue
figure for that month was in line with other months. Thus, the annual revenue from demand charges would, in fact, be lower by around Rs. 40 crores. Further,
the demand charges computed in the Tariff Order are as per the maximum demand
registered at each individual metering points.
The Order directs TPC to bill REL on the basis of Coincident Maximum
Demand (CMD). TPC contends that the
annual reduction in revenue due to demand charges based on CMD would be Rs.20
crores. Therefore, the Petition seeks that the Commission consider the impact
of these amounts on the Annual Revenue Requirement. TPC have sought review on
the basis of a mistake or error apparent from the face of the record, and also
relied on Regulations 92 and 96.
16. The Commission has also considered the further elaboration on
this matter by TPC in its affidavit dated 27th August, 2004. It notes that, by its very nature, the
exercise of tariff determination for any prospective period involves
estimations and projections based on a considered judgement of various factors.
There is, therefore, always the possibility of divergence between such
estimates and actuals, the net impact of which has to be assessed in the next
filing and tariff determination exercise, and considered appropriately at that
time through the regulatory dispensation.
Thus, it is premature at this stage to mandate any revenue recovery or
remedial measures. However, the
Commission is in the process of revisiting its Tariff Regulations (with the
involvement of TPC, among others), during which it could be examined as to
whether and how such matters could be addressed generically.
(3) HT
point of supply for residential complexes
17. Stating that TPC had proposed a new category of consumers in
their supplementary affidavit dated 23rd April, 2004 (the Commission
notes that this was a month after the public hearing), namely a HT point of
supply to residential complexes, the Petition states that TPC would like to
extend the same tariff to industrial and commercial complexes also. TPC have stated that the Commission has
approved the same in the REL and MSEB Tariff Orders. Review of the Tariff Order to introduce this dispensation is
sought claiming discovery of a new matter or evidence, or some mistake (or
omission) under Regulation 85. Regulations 92, 95 and 96 have also been cited.
18. The Commission notes that TPC are essentially seeking a basic
change in the duly determined tariff categorisation and structure, which is
clearly outside the scope of review, and have neither shown nor are seriously
claiming any mistake as such. TPC would have the opportunity to introduce such
proposals when they approach the Commission for tariff revision in future.
(4) Delayed
Payment Charges on Tax on Sale of Electricity.
19. Citing the provisions
for review under Regulation 85 on account of mistake or error apparent on the
face of record, TPC have submitted that the amount of Tax on Sale of
Electricity (TOSE) needs to be included in the calculation of Delayed Payment
Charges (DPC), since TOSE is payable to the State Government irrespective of
the actual recovery made by TPC from their consumers, whereas the Commission
has excluded this amount.
20. The Commission
notes that, under Section 3 and other provisions of the Maharashtra Tax on Sale
of Electricity Act, 1994, the onus of payment of TOSE to the State Govt. is
squarely on the concerned licensee, and the period within which such payments
are to be made by the licensee have also been prescribed. In case such payment
to the Govt. is delayed and DPC is payable by TPC, it cannot be passed on to
the consumers. The matter of any delay as between TPC and their consumers is
solely inter-se between them, and the Commission’s dispensation in this matter
(viz., to allow recovery DPC at the rate of 2% on the monthly electricity
bills, but excluding statutory levies and power factor penalty) has been a
considered one. TPC’s claim amounts to a substantive modification of this
dispensation, and is thus outside the scope of review.
(5) Minimum
Monthly Bill:
21. The Petition states that, as per the tariff prevailing prior to
the Commission’s Order, TPC have been preferring minimum monthly bills to
Disconnected/Shut down consumers by applying demand charges on 10% of the
Sanctioned Maximum Demand (SMD). TPC have sought that the new tariff should also
provide for billing on 10% minimum charges for giving concessions to such
consumers, and claim that this is an omission justifying review under
Regulation 85.
22. The Commission notes that TPC have not cited
any grounds to show that this was a mistake rather than its considered decision
considering the principle behind such charges. The earlier tariff structure
(which, in the case of TPC, had never undergone the Commission’s scrutiny
earlier) and TPC’s own proposals are far from being the only factors guiding
tariff determination. The Commission’s general thrust with regard to the
minimum charges of the type suggested by TPC for disconnected consumers can be
seen from the absence of such charges in its Tariff Orders in respect of MSEB
and REL.
(6) ToD
tariff to TPC for purchase from MSEB.
23. Citing the provisions in Regulation 85 regarding a new and
important matter or evidence which has come to light as justifying review, the
Petition states that the Commission has specified a ToD tariff with two slots
for sale of power from TPC to MSEB, but only a flat rate and not a ToD tariff
for MSEB’s sales to TPC.
24. The Commission notes that TPC’s concern has already been
addressed through para. 4 of the Corrigendum dated 11.6.2004 to the
operative/summary Order on the TPC tariff dated 1.6. 2004. The Corrigendum
provides for an additional charge of 25 paise per kWh for sale to MSEB from
0600 to 2200 hours.
Financial
Issues:
(1) Loss
on Exchange:
25. Citing a mistake or error apparent from the face of the record
as justifying review, TPC have sought that the exchange loss on account of the
difference between the opening exchange rate and the actual exchange rate at
the time of repayment should be allowed in computing the ARR since it has an
impact on cash outflow and profit & loss, and is not merely an accounting
adjustment as stated by the Commission. In their supplementary affidavit dated
27th August, 2004, TPC have requested the Commission to note this position and
record it as expenditure incurred by them for computing the ARR.
26. The Commission has already referred to differences between
estimates and future actuals referred at para. 16 above. However, it has noted
TPC’s concern. Moreover, this matter may also be examined generically while
revisiting the Tariff Regulations.
(2) FAC
calculations – removal of cap
27. Referring
to the cap of 10% of the variable component of tariff or increase in the Consumer
Price Index, whichever is lower, on the total Fuel Adjustment Cost (FAC)
charged to consumers in a year, TPC have sought that it be removed,
particularly since it is likely that the increase in the price of oil and
imported coal will be beyond 10% and not reflected in the Consumer Price Index,
and would thus adversely affect TPC’s revenue.
TPC have also asked that deviation may be allowed while approving the
FAC rate when it is not feasible to adhere to merit order despatch for various
emergent reasons.
28. The Commission notes that the plea for
removal of the cap on FAC charges is in the nature of a substantive
modification of a considered decision of the Commission. It may be mentioned that
the Commission had placed such a cap in the case of MSEB from as far back as
its Order dated 31st July, 2001 in separate proceedings. Beyond the
cap, adjustments can be made through future filings for tariff revision, and
the matter may also considered while revisiting the Tariff Regulations.
(3) Employee
Expenditure for 2004-05.
29. The Petition states that TPC had provided for Rs. 35 crores in
their ARR for 2004. Out of this amount,
there was a one-time expense (towards settlement of Gratuity) of Rs.14 crores,
which was not envisaged to be recurring.
However, the balance amount of Rs.21 crores was towards wage settlement,
and that is expected to recur in FY 2005 (as given in the Financial Model which
had been submitted by TPC) with an escalation over FY 2004 (taken as 10% in the
ARR). However, it appears that this
might not have been recognized by the Commission. The Petition seeks that TPC
be allowed this additional expenditure. Review is being sought arising from a
mistake or error apparent on the face of the record.
30. On this point, the Commission draws
attention to its observations at para.16 above.
With
these findings and observations, the Commission disposes of the present
Petition.
Sd/- Sd/- Sd/-
(Pramod Deo) (A. Velayutham) (P. Subrahmanyam)
Member
Member Chairman, MERC
Sd/-
(A.M.
Khan)
Secretary, MERC
|