13th floor, Centre No.1, World Trade Centre,
Cuffe Parade, Mumbai-400 005.
Tel. 22163964
/ 22163965, Fax No. 22163976
E-mail: mercindia@mercindia.com
Website: www.mercindia.com
Review of Order dated
16.6.2000, in respect of demand charges levied on M/s. Pudumjee Pulp & Paper Mills Ltd. considering CPP
synchronized with the grid, and related issues.
Dr. Pramod
Deo, Member
Dated: 7th February,
2005
This Petition has been filed on 6th
September 2004 by M/s. Pudumjee Pulp & Paper Mills Ltd. (“Pudumjee”), Pune
against the Maharashtra State Electricity Board (MSEB) as Respondents, with the
following prayers:
"(a) To declare that
the coercive steps taken by MSEB in sending supplementary bill dated 16.6.2001
to the sum of Rs.60,52,330/- are illegal and unjustified;
(b) To declare that issuance of supplementary bill dated 16.6.2001 for
amount of Rs.60,52,330/- by MSEB on the basis of audit report is contrary to
the law and amounts to the abuse of process of this Commission;
(c) To quash and set aside the supplementary bill dated 16.6.2001 of
Rs.60,52,330/- issued by MSEB under the guise of audit report;
(d) To grant such other relief as the Commission deems fit and proper
including directing MSEB to refund the amount of Rs.60,52,330/- with interest
at 18% p.a. "
2.
The Petition states
that Pudumjee is a High Tension consumer of MSEB paying around Rs.85 lakhs per month towards electricity
charges. In pursuance of Government of Maharashtra’s 1993 Industrial Policy
encouraging captive power generation, Pudumjee was granted consent by MSEB
under letter dated 22nd September 1998 for installing a 6.4 MW
Captive Power Plant (CPP) to run parallel with the MSEB grid at the supply
voltage of 22 KV, under Section 44 of the Electricity (Supply) Act, 1948 with
certain terms and conditions. The CPP was commissioned and synchronized with
the grid in December 1998. As per MSEB's High Tension Tariff effective from
1st September 1998, the Tariff rate mentioned was as under -
Demand charges Rs.180/- per month per KVA of billing demand
PLUS
Energy Charges 350 p/u +
FCA
Fuel Cost Adjustment (FCA) Charges as applicable from time to time.
Consumer having captive power plant synchronized with the Board’s
system shall pay demand charges at the rate of Rs.200/- KVA/month.
3.
The
Petition states that from 1998 the rate for billing by MSEB for energy consumed
by Pudumjee was Rs.180 on 75% of the contract demand. Pudumjee was never charged the additional component of Rs. 20
considering its CPP in any of the bills sent after December 1998.
4.
It
is further stated that MSEB submitted their proposal for revision of tariff
upon which the Commission passed an Order dated 28th April 2000. The
Petition contends that there was no reference to the concept of levy of
additional demand charges of Rs.20 by the MSEB in their first tariff revision
proposal to the Commission, and thus there was no mention of it in the
operative Order dated 28th April 2000 (and subsequent detailed Order
dated 5th May 2000) by which the first revision came into force.
5. The
Petition states that, pursuant to the tariff Order dated 5th May
2000, MSEB filed an Application dated 23rd May 2000 requesting the
Commission to consider some of the "practical difficulties" faced by
MSEB in the implementation and to issue suitable directives/ clarifications on
various matters. One such issue was regarding the demand charges for HT
consumers who have installed CPPs synchronized with the Board's system.
6.
The above issue was dealt with by the Commission in its Order dated 16th
June 2000, wherein it was clarified that HT consumers who have installed CPPs
synchronized with the MSEB system will be billed demand charges at the rate of
Rs.320/KVA/month for HTP-I and HTP-II categories (i.e. with an additional
component of Rs. 20 over and above the demand charges otherwise applicable),
and also that this matter would be taken up for further consideration at the
time of taking up issues relating to Section 22(1) of the then prevailing
Electricity Regulatory Commissions (ERC) Act, 1998. It is contended in the Petition that there was a violation of
principles of natural justice because no notice was issued to Pudumjee (a HT
consumer having CPP synchronized with the grid) before the Order dated 16th
June 2000 clarifying the above issue was passed on MSEB’s Application.
7. The
Petition states that, following the Order dated 16th June 2000,
under letter dated 16th June 2001, MSEB asked Pudumjee to pay around
Rs. 60.52 lakhs against a supplementary bill issued for alleged short billing
of the demand charges from December 1998 to May 2001. This composite bill of
Rs.60.52 lakhs can be divided into two parts, i.e. for the period from December
1998 to April 2000, prior to the Commission's Tariff Order, and for the period
subsequent to the Order, i.e. May 2000 to May, 2001. Since the first period was
prior to the Commission’s Order dated 5th May 2000, for the
supplementary bill for that period Pudumjee filed a Writ Petition before the
Bombay High Court (No.2567/02). However, it was dismissed in limine by the High
Court vide its Order dated 9th June 2003.
8. It was stated by MSEB that Pudumjee had been billed at Rs.180
and Rs.300 per KVA (pre and post revision) respectively instead of Rs.200
and Rs.320 per KVA, i.e. without the additional Rs. 20 component. According
to the Petition, from subsequent correspondence it transpired that this additional
demand was made by MSEB on the basis of the Commission’s Order fixing Rs.20
as additional demand charge from consumers having a CPP synchronized with
the grid, which was over and above the basic charge of Rs. 300 per KVA. Pudumjee
also learnt from the correspondence that, by its Order dated 16th
June 2000, the Commission allowed MSEB to charge Rs.20 as additional demand
charge, and the supplementary bill was raised with retrospective effect from
December 1998 onwards on that basis.
9. It
is further contended that, from December 1998 onwards, Pudumjee was billed at
the rate of Rs. 180/month, and from May 2000 at the rate of Rs. 300/month, both
without including the additional component of Rs.20. Thus, there was a
deliberate incorrect statement of fact made by MSEB in their Application dated
23rd May 2000 with respect to Pudumjee while seeking clarification
from the Commission. It is therefore submitted that the Commission may, in
exercise of its powers under Regulations 85 and 92, review its Order of 16th
June 2000 because, had the Commission been made aware of the correct and full
facts, that Order would not have been passed.
10. Pudumjee
has pointed out that, in addition to the Writ Petition filed in the Bombay High
Court, it also filed a Review Petition (Case No.30 of 2001) before the
Commission with respect to Orders dated 29th December 2001 and 10th
January 2002 in Case No.1/2000 r/w Order dated 5th May 2000 as
modified by Order dated 16th June 2000 in Case No.1/1999. The Review
Petition was disposed of by the Commission vide its Order dated 22nd
July 2004, but liberty was granted to Pudumjee to reapply with further grounds
for admission in terms of the Regulations governing review in case it was able
to do so subsequently, keeping in view the position recorded at paras 31 &
32 of the Order. Pudumjee has
accordingly filed the present Petition.
11. No
reply was received from MSEB upto the date of the admissibility hearing, which
was held on 18th October 2004, and at which Shri. Ramesh Darda,
Counsel for Pudumjee briefly reiterated the sequence of events and
correspondence set out in the Petition. Shri. Darda referred to the tariff
determined for MSEB's HTP-1 consumers in the Commission’s operative Order dated
28th April 2000, which was followed by the detailed tariff Order
dated 5th May 2000 in Case No.1 of 1999. He then referred to MSEB’s
Application dated 23rd May 2000 “Annexure 4-A, Page 64 of the
Petition) whereby MSEB requested the Commission to consider some of the
"practical difficulties" faced in implementation of the Tariff Order
dated 5th May 2000 and to issue suitable directives/clarifications
on various matters.
12. Citing
one of these issues, Counsel for Pudumjee referred to the following prayer /
request made by MSEB in its Application to the Commission (Page 69) -
The High Tension consumers who have installed Captive Generation plants and wherever these plants were synchronized with the Board system were billed demand charges at the rate of Rs.200/KVA/month (Rs.20 higher than HTP-I demand charge) instead of the demand charges is prevailing under HTP-I and HTP-II category. It is proposed to follow the same principles and consumers shall now be charged demand charges at the rate of Rs.320/KVA/month."
Counsel for Pudumjee stated
that this issue was dealt with at Para 7 (page 73) of the Commission’s Order
dated 16th June 2000 as follows:
"Demand Charges for
Captive Power Producers:-
The Commission clarifies that the high-tension consumers who have
installed captive generation plants and wherever these plants are synchronized
with the Board system will be billed demand charges at the rate of Rs.320/KVA/month
for HTP-I and HTP-II categories. However, this matter will be taken up for
further consideration at the time of taking up issues relating to Section 22(1)
of the ERC Act 1998. "
With
reference to the last sentence above, Counsel for Pudumjee stated that the
matter of standby charges for CPPs was finally settled by the Commission much
later, in its 3rd Tariff Order dated 10th March 2004. He
contended that there was no reference to the concept of additional demand
charges of Rs.20 by the MSEB in their first tariff revision proposal, and thus
there was no mention of it in the Commission's Orders dated 28th
April 2000 and 5th May 2000 by which the first revision came into
force.
13. Counsel
further submitted that Pudumjee was actually billed at the rate of Rs.180 per
month, and never at the rate of Rs.200/KVA/month. He contended that there had
been a violation of principles of natural justice because no notice was issued
to Pudumjee before the Order dated 16th June 2000 clarifying the
position was passed on MSEB's Application.
Hence, Pudumjee was not given an opportunity to set out the real
position before the Commission, which was that MSEB's Application dated 23rd
May 2000 did not give a true disclosure of the facts as regards Pudumjee, viz.
that there was another category of synchronized CPPs (including Pudumjee) to
whom demand charges of Rs.180/- rather than Rs. 200/KVA/month were applicable
and that, thus, the 16th June 2000 Order was passed by the
Commission without that knowledge. The Order could not, therefore, be treated
as binding upon Pudumjee. Pudumjee Counsel submitted that there were several
Supreme Court and High Court rulings to the effect that an Order which was
based on misrepresentation was not binding insofar as it related to any particular
party.
14. Counsel
for Pudumjee submitted that, following the Order dated 16th June
2000, MSEB sent a letter dated 16th June 2001 (Annexure-9, page 119)
to Pudumjee alongwith a supplementary bill amounting to Rs.60,52,330/- for the
period from December 1998 to May 2001 referring to the HT tariffs effective
from 1.9.1998 and 1.5.2000 (the latter being the tariff for synchronized CPPs as clarified by the Order dated
16.6.2000 in which Pudumjee was not noticed).
He argued that, in case there had been a shortfall in the levy, MSEB
could have followed the appropriate course for remedy.
15. Counsel
for Pudumjee submitted that this composite bill of Rs.60,52,330/- can be
divided into two parts, i.e. for the
period December 1998 to April 2000 prior to the Commission's Tariff Order (for
which the amount comes to Rs.37,40,646/-), and for the period subsequent to the
Order, i.e. May 2000 to May, 2001 (amounting to Rs.23,09,696/-). Since the first period was prior to the
Commission’s Order dated 5th May 2000, for the supplementary bill
for that period Pudumjee filed a Writ Petition before the Bombay High Court
(No.2567/02). However, it was dismissed in limine by the High Court vide Order
dated 9th June 2003 (Page 131). As the Writ Petition was dismissed
only on technical grounds and there were no conscious findings or adjudication
on questions of law or facts, Counsel for Pudumjee submitted that this
judgement did not operate as res judicata to estop it.
16. Counsel
for Pudumjee drew attention of the Commission to para 5 of page 3 of MSEB’s
Affidavit in Reply to the High Court, wherein there is a specific averment /
disclosure for the first time by MSEB that :
“…From 21st December 1998, through inadvertence the
Petitioners were charged demand charges at the rate of Rs.180 per KVA / month
instead of Rs.200/ KVA / month. The Respondent No.1 submits that in the month
of May 2001, in the course of Government audit it was noticed that the
Petitioners were charged demand charges at the rate of Rs.180/KVA/month instead
of Rs.200/KVA/month. To rectify the said mistake Respondent No.1 immediately
issued a supplementary bill dated 16th June 2001 amounting to
Rs.60.52 lacs.”
Counsel
for Pudumjee noted that, however, MSEB's 16th June 2001 letter does
not make any reference to inadvertence on their part. MSEB's letter to Pudumjee
only states that -
"Permission for captive power generation plant at your mill is granted
vide order dated 22/9/1998 and as per letter No.1864 dated 21/12/1998 your
plant is synchronized with the Board’s system in December 1998. As per Board’s
tariff for HT Consumer, rates for HT consumer is higher who are having CPP
synchronized with Board’s system under HTP-I. You have been billed at Rs.180
per KVA and Rs.300 per KVA respectively instead of Rs.200 and Rs.320 per KVA
from December 1998 to April 2000 and May 2000 to May 2001".
Counsel submitted that this
inadvertence on the part of MSEB is not condonable. If MSEB have acted negligently, then Pudumjee cannot be made to
suffer on that account. In their Affidavit in Reply filed before the High Court
in February 2003, MSEB have taken the stand that it was inadvertence on their
part, and that in the course of audit it was noticed that Pudumjee was charged
demand charges at the rate of Rs.180/KVA/month instead of Rs.200/KVA/month.
There is no mention of when the audit was done, but it must have been conducted
much earlier and was known to MSEB at the relevant time. He pointed out that the 16th June
2001 letter was issued by MSEB one full year after the Commission’s Order of
June 2000, during which period MSEB did nothing, nor did it seek to explain the
position to Pudumjee.
17. Counsel
for Pudumjee invited attention to Clause 10 (page 47) of the consent issued by
MSEB on 22nd September 1998 for installation of CPP synchronized
with the grid, and quoted one of the conditions as under –
"In case of the planned shut down of the CPP the excess demand recorded over and above the contract demand will be charged at double the normal demand charge rate of respective tariff in force from time to time. In case of unplanned shut down said demand will be charged at three times the normal demand charge rate of respective HT tariff in force from time to time. The event of planned shut down must be notified atleast three months in advance in writing to the MSEB. A unit can be shut down for annual overhaul only once in a year for a continuous period of one month."
Counsel submitted that,
thus, there were not only two types of CPPs (synchronized and not synchronized).
In cases of synchronized CPPs, MSEB also distinguished between planned and
unplanned shutdown for the purpose of levying charges.
18. Referring
to the HTP-I tariff applicable from 1st September 1998 (Page 50),
Pudumjee Counsel stated that demand charges were shown as Rs.180/KVA/month of
billing demand, and for CPPs synchronized with the grid they were
Rs.200/KVA/month. He stated that he wanted to demonstrate why Pudumjee was not
charged at Rs.200/KVA/month from that time, and that this was justified. In
their Application dated 23rd May 2000, MSEB had stated that they
were billing the CPP units synchronized with MSEB grid at the rate of
Rs.200. The Commission believed in the
correctness of that statement, which was not in fact true, and therefore,
without issuing notice to the concerned CPP holders, had accordingly allowed
MSEB to add that additional component of Rs.20 to the revised demand charges of
Rs.300.
19. Counsel
for Pudumjee then referred to MSEB’s letter dated 20th August 2001,
which was in reply to Pudumjee's objection to MSEB's letter of June, 2001, and
quoted as under -
1.
For the period before
1/5/2000 the demand charges are to be charged Rs.200 per KVA as per the provisions
in earlier tariff for the consumers having captive power plant synchronized
with Board’s system.
2. W.e.f. 1/5/2000 the demand charges are to be charged @ Rs.320/-
per KVA as per the revised tariff order
w.e.f. 1/5/2000 circulated vide our Departmental Circular (Commercial) No.646
dated 17/6/2000. This rate was shown in the MERC’s order dated 28/4/2000,
however, clarification was given by them, subsequently vide its order dated
16/6/2000 and in that it was ordered to charge Rs.320 per KVA for consumers
having captive power plant synchronized with Board system. "
Counsel for Pudumjee
submitted that, thus, MSEB had sought to put the onus for the additional Rs.20
charge (Rs. 300 + 20) for synchronized CPPs on the Commission through its Order
dated 16th June 2000 without mentioning that this was pursuant to
MSEB’s own Application following the Tariff Order, in which it was stated
incorrectly that this was the existing practice, and that it was on the basis
that the Commission had mandated it. Moreover, no notice was given to Pudumjee
while moving the Commission. It was a basic principle of law that, if a party
suffers on account of any action/Order, then it should be heard. He cited
rulings of the High Court in cases where Orders were based on non-disclosure of
facts. He submitted that this is not a case of bonafide mistake, for which the
Court places a rigorous test, i.e. full disclosure to it.
20. Pudumjee
Counsel submitted that the compilation of judgements circulated by him includes
High Court rulings on the wide scope of review, which is not limited to matters
such as errors apparent on the face of the record. Counsel further referred to
Regulations 85 & 92 of the Commission's Conduct of Business Regulations,
and quoted as under :
"85. Review of the decisions and directions and orders -
Any person aggrieved by directions, decisions or orders of the
Commission from which no appeal has been preferred or from which no appeal is
allowed and who, from the discovery of new and important matter of evidence
which after the exercise of due diligence was not within his knowledge or could
not be produced by him at the time when the directions, decisions or orders
were passed on account of some mistake or error apparent on the face of record
or for any other sufficient reasons he may apply for review of such order
within 45 days of the date of directions or decision or order as the case may
be to the Commission. "
"92. Saving of inherent power of the Commission
–
(i) Nothing in this regulation shall be deemed to limit or
otherwise affect the inherent power of the Commission to make such orders as
may be necessary for meeting the aims of justice or to prevent the abuse of the
process of the Commission.
(ii) Nothing
in the regulation shall bar the Commission from adopting in conformity with the
provisions of the Act, a procedure which is at variance with any of the
provisions of regulations including summary procedures if the Commission in
view of the special circumstance of the matter or class of matters and for
reasons to be recorded in writing deems it necessary or expedient for dealing
with such a matter or class of matters. Nothing in the regulation shall bar the
Commission to deal with any matter or exercise any power under the act for
which no regulation have been framed and the Commission may deal with such
matter, powers and functions in a manner it thinks fit."
Counsel
for Pudumjee submitted that Regulations 85 and 92 give ample power to the
Commission to review its Order of 16th June 2000. If it feels that the Order would not have
been passed had the Commission been made aware of the correct and full facts,
then there is nothing barring the Commission from going into it again. Regulation 81 was also quoted by him as
under –
"81. Interim orders investigation, enquiry,
collection of information, etc.-
The Commission may pass such interim or ad-interim orders, as the
Commission may consider appropriate at any stage of the proceedings having
regard to facts and circumstances of the case. The Commission may make such
order or orders as it thinks fit for collection of information, inquiry,
investigation, entry, search, seizure and, without prejudice to the generality
of its powers."
21. In view of the above Regulations, it was
submitted by Counsel for Pudumjee that, if the Commission is convinced of
Pudumjee’s submission that the 23rd May 2000 Application by MSEB
does not make true disclosure of facts and, as a result, Pudumjee has suffered
to the extent of Rs.60 lacs, then the Commission has the power to direct MSEB
to give a true disclosure of facts, especially in the context of the letter
dated 16th June 2001 and their submissions before the High
Court. If the Commission comes to the
conclusion that, prima facie, a case is made out by Pudumjee, then it calls for
a further inquiry in respect of the auditor’s report, and whether this is
really a matter arising only out of inadvertence.
22. Summarizing
Pudumjee's case, Counsel stated that the September 1998 tariff consisted of two
classes of HTP-I consumers, one to be billed at Rs.180 and the other to be
billed at Rs.200 (in case of CPPs synchronized with the grid). In addition to
these two, there was a 3rd category for CPPs synchronized with the
grid to be charged at Rs.180 as evidenced by the fact that, after making these
provisions, MSEB put Pudumjee into the category of Rs.180 from December 1998
upto May 2000 and charged it accordingly. This is a long period in which many
bills were raised by MSEB and also scrutinized by them and, therefore, this had
been consciously done inspite of Pudumjee being synchronized with the grid. He
submitted that, alternatively, MSEB had obtained the June, 2000 Order for
Rs.320 on the basis of misrepresentation and without full disclosure of facts.
Counsel for Pudumjee contended that MSEB have taken different stands before the
High Court, before the Commission and also before their consumers. If their
various stands put a consumer to a loss of Rs.60 lacs, then in all fairness
that consumer should be given an adequate opportunity of being heard.
23. Ms. Deepa Chawan, Counsel for MSEB
submitted that it was an admitted position that right from 1997 / 1998, i.e.
prior to the Commission's first Tariff Order, MSEB were charging this
additional component of Rs.20 to HTP consumers with CPPs synchronized with the
MSEB grid. After the operative Order dated 28th April 2000 and
detailed Tariff Order dated 5th May 2000, it was realised by MSEB
(not with specific reference to Pudumjee, but with general reference to that
whole category of consumers) that this component of Rs.20 relating to HTP
consumers who had CPPs synchronized with the MSEB grid had not been
considered. Hence, MSEB filed their
Application of 23rd May 2000, seeking clarification. She submitted
that the question of MSEB or the Commission giving notice to each consumer did
not arise because all those consumers were already liable to be billed and to
pay the additional Rs.20 as per the tariff prevailing from 1997/1998. Counsel
for MSEB further submitted that this additional component of Rs.20 was
explicitly continued in the Commission's 2nd Tariff Order of January
2002 also. That charge predated the
constitution of the Commission.
Therefore, the question of misrepresentation by MSEB does not arise.
24. MSEB Counsel submitted that, even
assuming that there was initially a mistake by some official, that could not
mandate a perpetuation of wrong billing. Counsel for MSEB further submitted
that when the audit in 2001 detected that MSEB were charging Pudumjee at the
rate of Rs.180 without taking into consideration that they are also a CPP
holder synchronized with MSEB grid, this levy of Rs.20, which was uniformly
chargeable to every such similarly situated consumer, had to be charged to
Pudumjee also. Therefore, MSEB issued the supplementary bill dated 16th
June 2001. Counsel submitted that, as a matter of fact, there was no third
category of HTP-I consumers with CPPs synchronized with the grid but who were
eligible for payment of demand charges at Rs.180 without the additional
component of Rs.20 as claimed by Pudumjee.
25. Counsel further referred to MSEB’s
Affidavit in Reply to the Writ Petition wherein MSEB had submitted to the High
Court that there was an error / lapse on their part which was pointed out by
the auditor, and that MSEB had accordingly corrected it. She also referred to
the High Court Order dated 9th June 2003, and quoted as under -
"The
Petitioners as high tension consumer were granted permission for Captive Power
Generation Plant on 22/9/98 and the said plant was synchronized with the
Board’s system in December 1998. The Petitioners were billed at Rs.180 per KVA
from December 1998 to April 2000. As per the existing tariff the Petitioners
were required to pay the charges @ Rs.200 per KVA per month. This mistake
appears to have been detected in the course of Government audit in the month of
May 2001 and accordingly the Petitioners were issued a supplementary bill dated
16/6/2001 amounting to Rs.60.52 Lacs. It is this bill which is under
challenge….
In the reply
affidavit, it has been submitted by the Respondents that the Petitioner
requested to the Respondents for payment of supplementary bill in installments,
which was granted and the Petitioners did pay the amount except for delayed
payment charges and the interest accrued thereon.”
Counsel for MSEB pointed out that this aspect was
not brought out by Counsel for Pudumjee before the Commission, and quoted
further as follows:
“On the face of High Tension tariff effective
from 1/10/98 it is clear that the consumers having captive power plant
synchronized with the Board system is required to pay demand charges @ Rs.200
per KVA per month. Admittedly the Petitioner’s captive power plant is
synchronized with Board’s system and accordingly, were liable to pay demand
charges at Rs.200 KVA per month. But instead by mistake the Petitioners were
billed at Rs.180 per month. Once the mistake was detected the supplementary
bill was issued by the Respondent. Immediately, upon receipt of the
supplementary bill the Petitioner did not challenge the same but instead prayed
for payment at installments, which seems to have been granted and paid. Mr.
Patel, learned Counsel for Petitioners however submitted that there is no
justification for demanding charges @ Rs.200 KVA per month for consumers having
captive power plant synchronized with Board’s system as it does not place any
additional burden on Board system.”
26. Counsel for MSEB pointed out that
Pudumjee had never challenged the levy of Rs.200 (i.e. the additional component
of Rs.20) on CPPs synchronized with the grid.
Pudumjee had only said that there was no justification for this levy.
She also submitted that Pudumjee’s Counsel had wanted to put in a supplementary
affidavit to challenge the charges of Rs.180+20 in the 1998 tariff, but the
High Court had said that it was too late, and quoted the High Court as follows
:
“He handed in
draft amendments seeking to amend the writ petition and to permit the
Petitioners to challenge the legality and the constitutionality of 1998 High
Tension Tariff to the extent it provided that consumers having captive power
plant synchronized with Board system shall pay demand charges at the rate of
Rs.200 KVA per month. We took into consideration this aspect and in our
considered view it is too late in the day for the Petitioners to raise a
grievance that the tariff fixed at the rate of Rs.200 KVA per month for
consumers having captive power plant synchronized with the Board system is
discriminatory.”
Counsel for MSEB submitted that the
High Tension Tariff with the additional Rs.20 component had been effective from
1st September 1998, and at no point of time did Pudumjee challenge
it. Pudumjee has also not made any
submissions on the delay in challenging it in their present Petition, and there
is no justification in permitting Pudumjee to do so at this stage.
27. Counsel for MSEB submitted that,
although the consumer with a CPP has his own power supply, when he is still
connected to MSEB the Board has to incur a fixed expenditure for the purpose.
Therefore, from 1998 onwards, MSEB have been levying an additional charge under
Section 49 of the Electricity (Supply) Act, and the Commission had agreed with
it by its Order dated 16th June 2000. Thereafter, that charge had
been continued by the Commission in subsequent tariff Orders, after following
due public process and scrutiny, uptil 1st December 2003. In these
circumstances, Counsel for MSEB queried as to whether the issue can be reopened
or reviewed at this stage. In the third Tariff Order, effective from 1st
December 2003, the Commission had modified this charge only to apply to the
standby component in excess of contract demand. Thereby the Commission had
addressed the matter further, as it had said it would in its Order dated
16.6.2000. It cannot be applied retrospectively, nor has Pudumjee asked the
Commission to do so.
28. Counsel
for MSEB further referred to the Commission’s Order (operative part of 2nd
tariff Order) dated 28th December 2001, subsequent to the 16th
June 2000 Order, which also touched upon the matter of Rs.20 component, and
quoted as under –
"Standby demand
charges:
HT Industrial
consumers having captive generation facilities synchronized with the grid, will
pay additional demand charges of Rs.20 per KVA per month. "
Counsel also referred to Clause 50 at Page 101 of
the Order dated 1st December 2003 whereby the Commission has
modified this levy of Rs.20 and quoted as under:
“The
additional standby charges of Rs.20 per KVA per month will be applicable to HT
industrial consumers with captive generating units synchronized with the MSEB
grid, only on the extent of standby demand, and not the entire contract demand
as prevalent currently.”
Counsel for MSEB explained
that the very fact that the Commission has used the term “prevalent currently”
means that it had taken note of the fact that MSEB were charging Rs. 20/KVA/month
throughout the period prior to this Order. She submitted that when a tariff is
decided by the Commission, it becomes effective from that date and it remains
so until the next tariff is decided. Therefore, she submitted that there was no
misrepresentation by MSEB as alleged by Pudumjee, and contended that this kind
of Petition amounts to an abuse of the process of law.
29. Counsel
for MSEB further argued that Pudumjee's Application seeks to go back to the
Order dated 16th June 2000 without even a mention of condonation of
delay. With regard to the plea that the Commission exercise its inherent
powers, Pudumjee was well aware in August 2001 itself that there was a
clarificatory Order passed by the Commission. There is no explanation given in
the Petition as to why Pudumjee has chosen to come before the Commission in
October 2004 with a grievance relating to alleged misrepresentation by MSEB in
the year 2000.
30. Counsel
for MSEB also referred to paras 31, 32 and 36 of the Commission’s last Order
dated 22nd July 2004 relating to Pudumjee in Case No.30 of 2001,
whereby liberty was given to Pudumjee to reapply to the Commission, and quoted
as under:
"31. Counsel
for MSEB submitted that the High Court, while dismissing Pudumjee’s Petition,
had referred to why the levy is being charged. It is not merely for
utilisation, but a fixed cost that MSEB incur for maintenance and capital cost.
She stated that she would circulate MSEB’s reply pertaining to the Writ
Petition and the Orders with MSEB’s affidavit for a clear picture. Counsel for
Pudumjee submitted that after examining MSEB’s reply, he would file a
rejoinder.
32. Counsel
for MSEB sought guidance from the Commission as to whether MSEB should wait for
High Court order in MSEB’s appeal (that is the appeal to challenge tariff
order) since it is yet to be pronounced, or file a reply, since it was on that
account that the present case has been in abeyance. However, that appeal
concerned several other matters. The Commission clarified that in this
particular case, since the Commission had passed another order in January 2002
dealing with the levy of Rs.20 per KVA, it had thought that it would hear
Pudumjee briefly, and Pudumjee may consider withdrawing the Petition in view of
the deliberations. Counsel for Pudumjee submitted that they were uncertain
about the concept of standby demand charges and, since the concept of standby
demand charges had been clarified by 1st December 2003 order, he
would take instructions and file an affidavit before the Commission after
examining the financial impact.”
She submitted that it was
only on this basis that the Commission granted liberty to Pudumjee to approach
it again.
"36. In view of the foregoing, the Commission declines to admit the Petition. However, Pudumjee are at liberty to reapply with further grounds for admission in terms of the Regulations governing review in case they are able to do so subsequently, keeping in view the position set out in paras 31 & 32 above.”
Thus,
in the above case, it was urged by Pudumjee that, having been uncertain about
the concept of standby demand charges and since the concept of standby demand
charges had been clarified by the 1st December 2003 Order, a fresh
affidavit would be filed before the Commission after examining the financial
impact, and the Commission had declined to admit the Petition with liberty to
reapply with further grounds for admission. But now what is urged by Pudumjee
before the Commission is something totally different and contrary to what was
urged last time. MSEB Counsel submitted that, therefore, the Petition should be
dismissed with costs.
31. Counsel for Pudumjee responded that its
case is specifically related to MSEB’s Application dated 23rd May
2000 and the Commission’s Order dated 16th June 2000. The concept of
standby charges is not mentioned in the tariff Order dated 5th May
2000. He further submitted that the concept of standby charges explained by the
Commission in the latest tariff Order is conceptually quite different from the
additional Rs.20 component in the 1998 and subsequent tariffs. Secondly, he
submitted that since MSEB, in their tariff revision proposal for the relevant
year, i.e. 2000-2001, were silent about the additional Rs.20, there was no
occasion for consumers to say anything about it during the tariff
proceedings. He referred to the latest
Tariff Order for FY 2003-04 and quoted para 2.2.3 as under -
"Para
2.2.3 Commission’s Ruling –
The Commission
has already elaborated the rationale for levy of demand charges in its previous
Tariff Orders. A major part of the costs of the MSEB, apart from cost of fuel
for own generation and variable cost of power purchase, is fixed in nature and
the ratio of fixed to variable costs currently stands at 53:47. Though the
consumer accesses electricity at any time he desires, the MSEB’s infrastructure
(physical infrastructure as well as employees, administration, etc.) has to be
permanently available, and related costs incurred irrespective of the level of
consumption by individual consumers, and these expenses thus comprises the
fixed costs of MSEB.
The Commission
has continued the process of increasing the recovery of fixed costs by levy of
fixed charges to consumers, to safeguard the MSEB from steep fluctuations in
revenue with varying consumption over time. The revised fixed/ demand charges
have been designed to recover around 40% of MSEB’s fixed costs, as compared to
the existing level of recovery of around 35% of fixed costs. The balanced fixed
costs are recovered through energy charges. Thus, for any disruption in supply,
the MSEB is effectively losing out on the recovery of fixed costs to that
extent. If MSEB is not allowed to recover fixed cost for the period of
interruptions and low voltage period, it would further affect the financial
viability of MSEB. At the same time, the Commission does not intend that the
consumers should suffer for the poor quality of supply from MSEB, and hereby
directs the MSEB to take all possible measures to maintain the voltages within
the prescribed limits, and to limit the load shedding hours to the minimum.”
“The Commission has considered the
representations of several industrial consumers in the context of charges
applicable for standby facility extended to the consumers by the MSEB. The
Commission hereby orders that the additional Standby charges of Rs.20 per KVA
per month will be applicable to HT industrial consumers with captive generating
units synchronized with MSEB grid, only on the extent of standby demand, and
not the entire contract demand as prevalent currently. Moreover, the Commission
accepts the rationale put forth by Pudumjee Pulp, that the standby charges
should be levied only if there is actual standby facility being extended by the
MSEB. There is no merit in the MSEB’s practice of levying additional demand
charges of Rs.20 per KVA per month on the entire billing demand despite the
fact that the billing demand has never exceeded the contract demand. In such
cases the MSEB is not really offering any standby facility, and is only
supplying within the consumer’s contract demand. Hence, standby charges will be
levied on such consumers on the standby component, only if the consumer’s demand
exceeds the contracted demand.”
32. Counsel for Pudumjee noted that the
Commission had specifically mentioned Pudumjee in the above Tariff Order. Further, the Commission itself had finally
rejected the practice of MSEB levying of the component of Rs.20 on the entire
billing demand, and introduced a new concept of standby charge. The Writ Petition filed by Pudumjee in the
High Court was dismissed on technical grounds. The High Court had also stated
only that it was too late for Pudumjee to amend its Petition to challenge the
1998 tariff. Therefore, Counsel submitted that the High Court Order does not
prevent Pudumjee’s present claim. Further, Regulations 85 and 92 allow
reopening of the matter, and the Commission’s Order dated 22nd July
2004 itself grant permission to Pudumjee to reapply with further grounds for
admission. Accordingly, Pudumjee has approached the Commission again within 45
days of that Order. To the Commission’s observation that the dispensation in
the last tariff Order is prospective, Counsel submitted that his case is that
there is no connection between the concept of standby charge introduced in the
latest tariff Order, and the additional Rs.20 component billed prior to that to
Pudumjee by MSEB, after it had been charged without this additional component
till mid 2001.
33. Subsequent
to circulation of the Record of the hearing, Pudumjee made a further written
submission, essentially reiterating its contentions in brief and challenging
MSEB Counsel's various statements made during the hearing as incorrect.
34. The
Commission notes that, in its Order dated 22nd July, 2004 on
Pudumjee's earlier Petition (Case No. 30 of 2001), it had stated (at paras 35
and 36) that:
"The Commission notes
that both the issues of which review is sought, viz. withdrawal of the
additional charge of Rs 20/- per KVA and the reliability charge, are
substantive elements of the impugned tariff and related Orders, and have been
further amplified in the Commission's latest tariff Order. These Orders have been passed after
following due process and consideration, and public hearings where
required. Keeping in view the
deliberations at the hearing held on 12th January, 2004 and the
observations made, the Commission finds that the present Petition does not meet
the test of the provisions in the Regulations governing review, either in terms
of any prima facie error apparent on the face of record or any other mistake,
or new facts, or any other sufficient reason.
Under the Regulations, the ambit of review is circumscribed, and the
Commission cannot entertain what is essentially an appeal against its Orders in
the guise of such review. That would
amount to ascribing to itself the powers of the competent appellate authority
under the law. Moreover, the Commission
has waited for considerable time for a further filing by Pudumjee, which has
not been forthcoming uptil now.
In view of the foregoing, the Commission
declines to admit the Petition.
However, Pudumjee are at liberty to reapply with further grounds for
admission in terms of the Regulations governing review in case they are able to
do so subsequently, keeping in view the position set out at paras 31 and 32
above."
Thereafter,
Pudumjee have filed the present Petition with the prayers set out in the 1st
para of this Order. These prayers
essentially require a review of the Commission's Order dated 16th June,
2000 and related matters. It is,
therefore, worthwhile setting out again the provisions of Regulations 85 of the
MERC (Conduct of Business)Regulations, 2004 (which is similar to Regulation 87
of the earlier Regulations of 1999):
"85. Review of decisions, directions and orders-
(a) Any person aggrieved by a direction, decision
or order of the Commission, from which (i) no appeal has been preferred or (ii)
from which no appeal is allowed, may, upon the discovery of new and important
matter or evidence which, after the exercise of due diligence, was not within
his knowledge or could not be produced by him at the time when the direction,
decision or order was passed or on account of some mistake or error apparent
from the face of the record, or for any other sufficient reasons, may apply for
a review of such order, within forty-five days of the date of the direction,
decision or order, as the case may be, to the Commission…
… (d) When it appears to the Commission that there
is no sufficient ground for review, the Commission shall reject such review
application.
(e) When the Commission is of the opinion that
the review application should be granted, it shall grant the same provided that
no such application will be granted without previous notice to the opposite
side or party to enable him to appear and to be heard in support of the
decision or order, the review of which is applied for."
35. The
main ground for review sought by Pudumjee is that the Commission's Order dated
16th June, 2000 was based on an Application from MSEB subsequent to
the 1st tariff Order. That Application
stated, inter alia, that there was a pre-existing and ongoing dispensation to
the effect that HT consumers with Captive Power Plants (CPP) synchronized with
the grid were liable to pay an additional amount of Rs 20/- per KVA/month over
and above the demand charges (earlier Rs 180/-) for other HT consumers. Pudumjee's contention is that MSEB had
misrepresented the facts to the Commission inasmuch as Pudumjee was being
billed ever since the tariff revision in 1998 at Rs 180/- and that, thus, there
was in effect a third category of HT consumers, viz. those with CPPs
synchronized with the grid who were liable to pay demand charges without the
additional Rs 20/-. Thus, the
Commission's Order was based on misrepresentation of the facts by MSEB, which
would have been pointed out by Pudumjee
had it been noticed and given an opportunity to be heard. Once this position is accepted, Pudumjee has
put forward various other contentions regarding the merits or otherwise of that
additional component and the logic of making such a distinction between HT
consumers..
36. It
is a matter of record, and Pudumjee has itself quoted in its Petition (as
mentioned at para 2 above), that in MSEB's HT tariff effective from 1st
September, 1998, as against demand charges of Rs 180/- per month/ per kVA of
billing demand, consumers with CPPs synchronized with the MSEB system are to
pay demand charges @ Rs 200/- per month/ per KVA/month, i.e. paying an
additional amount of Rs 20/-. Pudumjee
has at no stage shown from the 1998 tariff or any other document that, apart
from this, there was another category of such CPP holders who were liable to
pay demand charges without this additionality, relying instead on the factual
circumstance that, till June, 2001, it was not asked to pay it as indicating
the existence of such a third category.
MSEB have fairly admitted an error on their part, both in the High Court
and before the Commission, in wrongly charging Pudumjee without this component
although its CPP was synchronized with the grid. The fact of such erroneous billing cannot possibly be treated as
tantamount to the existence of any other tariff category which has not been
duly mandated, though it reflects poorly on the diligence that MSEB should have
exercised, particularly since the mistake was not rectified till one year after
the Commission's Order dated 16th June, 2000. Pudumjee's other averment regarding the
distinction made by MSEB in cases of planned and unplanned shut down while
charging for exceeding contract demand (cited at para 14 above) is unrelated to
the additional component of Rs 20/-.
Thus, the Commission finds no misrepresentation on this account by MSEB
when they applied in May, 2000 after the tariff Order citing the general
dispensation in this regard. As a
result, the question of review of that and related Orders does not arise considering the provisions of the
Regulations.
37. As
far as the challenge to the additional component itself is concerned, it
therefore becomes a subject matter for appeal, which is beyond the Commission's
jurisdiction. The Commission notes,
however, that Pudumjee had sought to reopen the 1998 tariff on this count
before the High Court, but was denied.
While retaining the additional Rs 20/- component in its 2nd tariff
Order, the Commission had subsequently altered its basis in its last tariff
Order effective from December 2003, but this is not relevant to the immediate
issue before us. However, it may be
mentioned that, during the course of the earlier proceedings, the Commission
had also briefly set out the rationale for this charge.
38. In
any case, considering the above, the question of the Commission requiring to exercise its powers under
Regulation 92 also does not arise.
Before concluding the matter, it may only be mentioned that, at para 8
of the Petition, Pudumjee has also stated that:
"It is also a fact borne
from the record that Applicant have not run CPP through relevant period in
synchronization with MSEB grid and non Applicant did not ascertain this fact at
any point of time."
This point was not
elaborated by Pudumjee further and, indeed, it has nothing to do with the main
arguments for review or for doing away with the charge, but relates to the
implementation of the tariff as applied from time to time, and may be dealt
with by the parties separately..
The Commission disposes of
Pudumjee's Petition accordingly.
| Sd/- | Sd/- | |
| (A. Velayutham) | (Pramod Deo) | |
| Member | Member | |
|
Sd/-
|
||
|
(A.M.
Khan)
|
||
|
Secretary,
MERC
|
|
|