Before the
World Trade
Centre, Centre No.1, 13th floor, Cuffe Parade, Mumbai 400 005.
Tel. No. 022
22163964/65/69 – Fax 022 22163976
E-mail mercindia@mercindia.com
Website: www.Mercindia.com
In the matter of
Change of category
from Sizing to Powerloom and related matters.
Shri P. Subrahmanyam, Chairman
Shri Jayant Deo, Member
Dr Pramod Deo,
Member
In his
Petition dated 7th
August, 2003, seeking a change in category for his unit from sizing to
powerloom and related matters, Shri Husain Abdul Hamid has stated that he had
a 3-phase connection at his
work-shed in Islampura Ward, Malegaon, Dist. Nashik for the purposes of
industrial use, i.e. sizing process.
However, due to various difficulties, he had sought a change in category
from sizing to Powerloom, and applied to the local office of the Maharashtra
State Electricity Board (MSEB) on 22nd December, 2000, and by two
communications in February, 2001. After
closing down his sizing activity, he made several visits to the MSEB office,
without result. Thereafter, he informed
the concerned MSEB officials that he had installed machinery and 11 power looms
requiring 11.25 HP load. Shri Hamid has
stated that, because of labour and financial difficulties, he was working in
only a single shift at different times.
Taking this into account and attaching further details, he has also
complained about the billing. Shri
Hamid has submitted that there are no arrears against his 3-phase connection
for sizing and has also been paying bills regularly since January, 2002.
2. Shri
Hamid has made various allegations against the concerned MSEB Sub-Engineer,
whom he claims visited his work-shed several times and asked for a bribe. The Petition states that, upto August 2002,
his sanctioned load was 10 HP but he had applied to MSEB for an increase. He was given a firm quotation, complied with
all the formalities and actually increased the load, for which he had to pay
the Sub-Engineer. Thereafter, in
October 2002, money was also demanded from him for rectification of his bill
considering the fact that his unit was closed since August 2002. The Petition alleges that demands for money
continued thereafter, and a tout was also sent to him. He has also cited various false reports
regarding faulty meter, etc. given by the
Sub-Engineer to MSEB. Finally,
in the absence of any other alternative and under duress, on 27th February,
2003, Shri Hamid paid an excess bill of more than Rs 47,000/-. Thereafter, in July, 2003, after more
demands for money, his meter was removed.
3. In
response to a letter of the Commission asking him to clarify the provisions of
the Electricity Act (EA), 2003 under which he has approached the Commission,
under his letter dated 15th September, 2003 Shri Hamid reiterated that he had
applied without result to MSEB for a change of category from sizing process for
which he was on LT (LTPG tariff) to powerloom.
Shri Hamid submitted that his Petition falls within the purview of
Section 43 of EA, 2003, under which MSEB have to supply electricity within a month
of application. His case does not fall
under Section 43(2) (where the time limit can be extended) because there is
already an existing supply line and he had only asked for change of
category. However, since MSEB had not
done so within the stipulated period, they were liable to punishment under
Section 43(3). Shri Hamid submitted
further that his electricity supply was temporarily disconnected from August,
2002, after which he had deposited around Rs 47,000/- in February, 2003 in good
faith.
4. Shri
Hamid followed up with a letter dated 29th September, 2003. Referring to his Petition, where he had
stated that MSEB had removed his meter on 16th July, 2003, Shri Hamid stated
that, on 19th August, 2003, the service wire was also removed and, although there
was no visit from the Flying Squad, a false FIR alleging theft was lodged with
the police even though his unit was closed since August, 2002. The news of the alleged theft case was also
reported in the press. The police
complaint alleges theft to the extent of 2.47 lakh units.
5. Under
another letter dated 6th October, 2003, Shri Hamid has provided further details
of the sequence in his case with copies of challenged bills/ receipts and meter
readings. Another letter followed on
21st October, 2003 containing further details and allegations.
6. In
their Reply dated 5th November, 2003, MSEB have stated that the Petitioner had
an industrial connection for undertaking sizing work. He applied for change of category from sizing to powerloom vide
the three applications cited by
him. MSEB had informed him under letter
dated 8th February, 2001 that a No Objection Certificate from the Municipal
Council (being the local authority) was needed for the required load and
purpose. The necessary certificate from
the Textile Commissioner was also not given.
MSEB have pointed out that, as admitted by Shri Hamid, he had started the powerloom activity even
before the transfer was sanctioned. The
required documents have not been furnished to MSEB so far.
7. MSEB's
Reply also states that Shri Hamid has been in arrears of bills in respect of
his electric connection, and had denied his contention of regular payment or
that the production had stopped from August, 2002. MSEB have stated that Shri Hamid never raised any dispute about
the bills for the period after August 2002 till 28th February, 2003. For this period, the arrears increased from
around Rs 52,000/- to Rs 1.04 lakhs. In
fact, in his complaint dated 7th January, 2003, Shri Hamid had only
said that the bill for the said period has not been received. MSEB have stated further that site
inspection revealed that electricity had been consumed during that period and
the production process was on. Shri
Hamid was also given copies of all the relevant documents. However, as recorded by the concerned Dy.
Exe. Engineer under his letter dated 24th September, 2003, Shri Hamid failed to
make even any provisional payment.
8. In
their Reply, MSEB have stated that, due to the mounting arrears, supply was
temporarily disconnected on 16th July, 2003.
However, during the spot inspection on 26th August, 2003, it was found
that, in spite of temporary disconnection, Shri Hamid had illegally reconnected
it. On 2nd August, 2003, a notice in
respect of proposed permanent disconnection was given and the electric supply
was permanently disconnected on 26th August, 2003. On 26th September, 2003, the Area Engineer filed a FIR for theft.
9. As
regards the allegations made regarding certain officials, an inquiry was
conducted by the Exe.Engineer (UCR Malegaon) and revealed that the allegations
were false and motivated.
10. MSEB
have further stated that Shri Hamid had been using electric connection contrary
to the authorization which was given, inasmuch as he had increased the load to
26 HP.
11. According
to MSEB's Reply, Shri Hamid submitted a complaint disputing the arrears on 28th
February, 2003. He failed to make
payments even after temporary disconnection on 16th July, 2003. The Exe. Engineer (UCR Malegaon) has also
observed that the meter was unauthorizedly handled, thereby stopping it, as per
the spot verification report of October 2002 and January 2003. MSEB have, therefore, sought that the
Petition be summarily dismissed.
12. In
his Rejoinder submitted at the hearing held on 10th December, 2003, Shri Hamid
has stated that, with his application for change of category, he had attached a
NoC dated 3rd February, 2001 from the Municipal Council in compliance of MSEB's
letter dated 2nd February, 2001. (The
NOC states that it is for a "Tarashan machine", and for 5 HP). MSEB's letter seeking this compliance had
not asked for a certificate from the Textile Commissioner, and is also
enclosed. This requirement was brought
up for the first time in MSEB's reply.
13. Shri
Hamid reiterated that no arrears were outstanding and the production process
stopped in August 2002. However, MSEB
illegally issued bills for the subsequent period till March 2003 for alleged
arrears of Rs 52,000/- which went up to Rs 1.04 lakhs. These amounts were subsequently corrected to
around Rs 47,000/-. The corrected bill
was prepared as per the flat rate applicable per powerloom for 26 looms for 7
months, a copy of which has been attached.
In his Rejoinder, Shri Hamid states that the Sub-Engineer compelled him
to pay this above amount, saying that it was necessary so that the abnormal and
faulty bill could be revised and the category changed. Therefore, Shri Hamid did so in good faith
and was given a receipt dated 27th February, 2003.
14. Shri
Hamid has stated that the allegation that the work site revealed that
electricity was consumed during this period and that the production process was
on is false and concocted. The spot
verification report dated 17th August, 2002 and 8th January, 2003 which have
been enclosed, themselves reveal that the powerlooms were not functioning and
no production process was in progress, and comments that the seals were
intact. Shri Hamid denies the various
other statements made by MSEB in their Reply and reiterates his earlier contentions
and allegations. He has stated that,
when he refused to meet the further demands of the Sub-Engineer, a false FIR
was filed claiming theft to the extent of Rs 11.16 lakhs for the period of 3
years from August 2000 to July 2003, which is clearly in contradiction of
MSEB's own spot verification reports.
Moreover, the meter reader visits the premises each month.
15. In
respect of the increase in load to 19 HP and then to 26 HP, Shri Hamid states
that MSEB have suppressed the fact that they are collecting the overload
penalty from him. He has sought that
reconnection of electricity supply and change of category from sizing to
powerloom unit be directed by the Commission, and that the bills raised after
August 2002 and upto 26th August, 2003 be invalidated and only minimum demand
charge levied since his unit was closed during that period.
16. At
the hearing held on 10th December, 2003 Shri N.A. Lodhi, Counsel for Shri Hamid
submitted that the Petitioner originally obtained a connection for his sizing unit. A sizing unit is a part and parcel of a
powerloom unit, and not a different unit.
Thereafter, he applied for a change of category since he stopped
undertaking the sizing process in view of various difficulties. He reiterated the sequence of events contained
in the Petition and subsequent submissions.
He submitted that it is only now, through MSEB's Reply, that Shri Hamid
has been informed of the requirement of a registration certificate from the
Textile Commissioner. While agreeing
with the Commission that he has to fulfill whatever requirements there might
be, Counsel pointed out that, when he applied, he was asked to produce only a
certificate from the Municipal Council, which he did. If MSEB required some other certificate, it would also be produced
but MSEB could not disconnect Shri Hamid or not allow him to run his powerloom
business, which is his source of livelihood.
17. To a
query by the Commission, Shri Gaurang Joshi, Counsel for MSEB stated that Shri
Hamid had applied for a higher connected load of 19 HP and was asked to produce
various NOCs. MSEB have been asking for
this on instructions from the State Govt. and it has been part of MSEB's
procedures since 1998 in respect of powerlooms for which a Circular had been
issued. He conceded that all the bills
had been paid for the sizing unit, but there had been default after the change
over to powerloom unauthorizedly. The
Commission observed that MSEB have continued to charge Shri Hamid at the higher
LTPG tariff rather than the tariff for powerloom. MSEB's case seems to be that Shri Hamid did apply, but has not
given certain documents, or the documents given by him are not the correct
one. MSEB Counsel submitted that Shri
Hamid had also given certain documents which cannot be co-related to his
premises.
18. The
Commission observed that new Regulations have been put in place today with
regard to the mechanism for settlement of grievances such as this. The Commission also cited the definition of
'grievance' contained in the Regulations.
MSEB should endeavour to resolve the position with regard to
disconnection and change of category and verification of arrears of the
Petitioner through their internal redressal mechanism within one month. Compliance should also be filed. Counsel for MSEB stated that MSEB would
approach the Petitioner accordingly, but pointed out that a case of theft has
also been registered. Moreover, there
is an Order of the Commission (Case No. 24 of 2001) that no change of category
can be effected without the Commission's approval.
19. Referring
to the above directions given by the Commission at the hearing, CE (Comm), MSEB
wrote to the Petitioner on 29th December, 2003 to approach the concerned Suptd.
Engineer, Nashik Circle with a view to redressal of his grievances. However, under letter dated 29th March, 2004
(with copy endorsed to the Commission), the Suptd. Engineer referred to Shri
Hamid's grievance application and visits to the concerned office, intimated
Petitioner's Counsel that the NOC from Malegaon Municipal Council is for
'Tarashan' machinery and not for powerloom.
Various other averments have also been made, including a defence of the
police case filed since the spot verification report "shows reverse trend". The NOC from the Textile Commissioner, and also
from the Municipal authorities clearly stating the activity as powerloom and
the specific location have also been asked for.
20. In
view of the continuing impasse in this case, the Commission disposes of the
Petition with the following directions:
(i)
While
noting that when the Petitioner first applied for change of category, he was
only asked for clearance from the Municipal Council, but no certificate from
the Textile Commissioner or other authorities concerned with powerlooms, MSEB
should communicate their final decision with regard to change of category upon
receipt of the apparently wanting certificates or documents already
communicated to him.
(ii)
While
the Commission would not like to interfere in matters where theft is alleged
and cases have been lodged which are governed by separate provisions of EA,
2003, the contents of the spot verification reports furnished by MSEB to the
Petitioner and which have been filed by him indicate that it is necessary for
MSEB to review the basis on which the theft charge has been lodged with the
police authorities, and to withdraw it if considered appropriate after such
review.
(iii)
As
far as the claims for payment/ arrears for the period from August, 2002 onwards
is concerned, it is admitted by MSEB that the alleged consumption has been in
respect of powerlooms. Hence, the claim
should provisionally be on the basis of the powerloom tariff.
21. MSEB should file the detailed status of compliance of the above directions, with a copy to the Petitioner, within one month. In case the Petitioner is dis-satisfied with MSEB's final decision, to the extent that they fall within the ambit of the term 'grievance' as defined in the Regulations, he also has recourse to the Consumer Grievance Redressal Forum set up for the Nashik Zone of MSEB.
22. With regard to MSEB's contention that, in Case No. 24 of 2001 concerning the MIDC Murbad Industrial Area, the Commission had restricted change of category without its prior approval, the Commission notes that a Clarificatory Order has been issued on 19th July, 2004 which deals with such cases.
| Sd/- | Sd/- | Sd/- | |
| (Jayant Deo) | (Dr Pramod Deo) | (P. Subrahmanyam) |
|
| Member | Member | Chairman, MERC |
|
Sd/- |
|||
| (A.M. Khan) | |||
| Secretary, MERC | |||
|
|||