Before the
World Trade Centre, Centre No.1, 13th floor,
Cuffe Parade, Mumbai 400 005.
Tel. No. 022 22163964/65/69 – Fax 022 22163976
E-mail mercindia@mercindia.com
Website: www.Mercindia.com
In the matter of
Review of Tariff Order dated 10.03.2004
with regard to load factor and other incentives.
Shri P. Subrahmanyam, Chairman
Shri Jayant Deo, Member
Dr Pramod Deo, Member
In their Petition
filed on 5th May, 2004, M/s. Balaji Electro Smelters Ltd. (BESL), Yavatmal have
sought review of the Commission's tariff Order dated 10th March, 2004 in
respect of the Maharashtra State Electricity Board (MSEB) with regard to the
provisions for Load Factor Incentive (LFI), with the following prayers:
"a) To consider to deduct 60 hours from total
number of hours in a month, while calculating maximum consumption possible to
enable to avail maximum Load Factor Incentives of 15% to consumer.
b)
To consider squaring up of higher unit if load factor is
above 0.5%.
c)
To allow LFI even if any unit exceeds contract demand upto
5% in view of practical difficulties in controlling contract demand.
d)
To allow LFI to Petitioner for the month of February 2004
MSEB bill.
e)
To direct Respondent to allow incentive amount during the
same month if a consumer pays bill within seven days."
2. The Petition
states that MSEB are giving the benefit of LFI, which was provided in the Order
dated 10th March, 2004, as follows:
i)
Deduction of actual planned Load Shedding hours from the total
number of hours (No. of days X 24) in a billing month.
ii)
If load factor is above 0.5%, MSEB are squaring up to the lower digit,
e.g. if the load factor is 87.60%, it is considered as 87%.
iii)
Further, if MSEB undertakes planned load shedding for 60 hours a
month, the load factor will be 91.67% (660 hours / 720 hours) even if a
consumer maintains 100% efficiency.
Hence, even if 100% efficiency is maintained, no consumer can achieve a
load factor of 92.50% to avail of maximum LFI of 15%.
3. The Petition
refers to the Load Factor formula in the Order. The Commission notes that the maximum consumption possible (the
denominator of the formula) is equal to the Contract Demand X Actual Power
Factor X (total hours during the month less planned load shedding hours), and
the Order states that interruption/ non-supply to the extent of 60 hours in a
month is built into this scheme. In this
context, the Petition states that every industry has to resort to shut downs
due to repairs, maintenance, etc. as also done by MSEB through load shedding.
Therefore, the Commission should consider deducting 60 hours from the total
number of hours during a month. For
example, if the total number of hours in a month are 720, MSEB should deduct 60
hours (660 hours). In such case, if a
consumer maintains 100% efficiency, load factor will be 100% (660 hours / 660
hours). It would then be possible to
achieve load factor of 92.50% after repairs and maintenance by any consumer,
which would be fair and just.
4. With regard to
rounding off, the Petition urges that squaring up should be done to the next
higher digit if the load factor is above 0.5%.
Thus, if the load factor achieved is 87.60%, it should be squared up to
88%.
5. The Petition
states that the Order provides that, if the billing demand exceeds the contract
demand, the LFI would not be applicable since, in such circumstances, the MSEB
system is subjected to stress and load management will become difficult. However, the Petition points out that MSEB
are charging a penalty for exceeding contract demand. There are also practical difficulties in controlling contract
demand, viz.
(a)
to achieve higher load factor, a consumer has to run at maximum
Contract Demand.
(b)
there are no equipments to precisely control the Contract
Demand. There is a variation of upto
5%. For example, if a consumer has
contract demand of 3,000 KVA, there is a variation of 2,850 KVA to 3150 KVA for
controlling the contract demand.
(c)
C.T. & P.T. ratios, accuracy, cable length and time setting
differ as between the consumer and MSEB.
There is a variation of Contract Demand upto 3% on this account.
For these reasons, the Petition seeks that
LFI be allowed even if the contract demand is exceeded upto 5%. Even though BESL exceeded their contract
demand by only 0.1% in respect of the bill for February, 2004, MSEB did not
allow LFI for that month. The Petition
argues that, since this was prior to the Commission's Order dated 10th March,
2004 in which it was stated that units exceeding contract demand would not be
entitled for LFI during the relevant month, and also since BESL have not done
so intentionally, MSEB should allow them LFI in respect of the bill for
February, 2004.
6. The Petition
states that MSEB are allowing load factor, power factor and bulk discount
incentives to eligible consumers in the next month, and urged that the
incentive amounts should be passed on the same month.
7. In their Reply
dated 25th May, 2004, MSEB have submitted that the review Petition is not
maintainable in law. BESL are, in fact,
seeking modification of the Order dated 10th March, 2004 and the Commission
ought, therefore, to reject the Petition on this ground itself. Citing the provisions of the Conduct of
Business Regulations, MSEB have submitted that the scope of review is very
limited and can be allowed on only the three grounds which have been cited in
Regulation 87.
8. MSEB have
submitted further that BESL have erred in calculating the maximum possible load
factor by deducting planned load shedding hours from the numerator of the Load
Factor formula. In fact, MSEB are
deducting planned load shedding hours from the denominator as per the Commission's
formula, which is used by MSEB for calculating load factor for all
consumers. MSEB contend that it is
possible for consumers to achieve a load factor of 93% and avail of LFI to the
maximum possible extent.
9. Quoting from para
32.1.3 of the tariff Order, MSEB's Reply states that the calculation of LFI is
for every percentage point of increase in load factor, and there is no question
of MSEB squaring up the load factor as suggested in the Petition.
10. With regard to the
position when Contract Demand is exceeded, MSEB have pointed out that the
system is designed to cater to the Contract Demand specified by the consumers
themselves, and in its Order the Commission has drawn attention to the problems
that arise when it is exceeded. MSEB
have further stated that in case BESL are experiencing difficulty in limiting
billing demand to the extent of Contract Demand, they can approach MSEB for an
increase in the Contract Demand. With a
small increase in Contract Demand and no change in billing demand, they will
still be eligible for the maximum LFI.
Since the Commission's Order does not provide for it, BESL cannot seek
allowance of LFI if the billing demand exceeds Contract Demand by upto 5%
through a review Petition.
11. With regard to
BESL's arguments regarding the instance of February, 2004 predating
Commission's Order, MSEB have pointed out that the Order expressly states that
it is applicable from 1st December, 2003.
12. With regard to
providing the incentives in the same month, MSEB have stated that, in such an
event, if the consumer does not pay the bill within the stipulated period, MSEB
will have to reverse the amount in the next bill, and so on. This will needlessly increase the complexity
of the billing process. Moreover, once
the billing has been completed for a month, it is practically not possible for
MSEB to provide incentive in that month.
13. In their Rejoinder
dated 16th June, 2004, which also seeks to respond to the Commission's letter
asking them to clarify how the Petition meets the requirement of review under
its Conduct of Business Regulations, BESL have submitted that, since the matter
has not been challenged by way of an appeal or Writ Petition by them, BESL have
every right to seek review. They have
cited the Supreme Court Judgement reported in AIR 2002 (Page 1402) in the case
of Kalpataru Agro Forest Enterprises vs. Union of India (no copy was
submitted), where it had been held that a decree or order from which no appeal
has been filed can be reviewed, and argued that this principle is applicable to
the present case. Regulation 87 states
that a party may apply for review of an Order arising from the discovery of new
and important matter or evidence which after exercise of due diligence was not
within the knowledge of the party or could not be produced at the time of
decision. BESL have submitted that the
"theory" of LFI was introduced for the first time by the Order dated
10th March, 2004. Hence, BESL were not
aware of it during part of the relevant period and could not produce any
evidence on this point prior to the Order.
Regulation 87 also provides for filing of a review Petition for any
other sufficient reason, and BESL have argued that such reasons and grounds
have been given. BESL's Rejoinder also
points out that, even prior to the final Order, and after the operative Order
was passed, they had sought clarifications on 20th December, 2003 from the
Commission regarding the definition of Contract Demand, LFI and its
applicability, etc. Even though there
was no provision in the Regulations, the Commission had given the clarification
in the detailed Order. That, impliedly,
was nothing but a review. Further,
under Regulation 24, the Commission has the power to hear affected or
interested persons and also to initiate any proceedings suo moto. BESL are an interested and affected party
and, therefore, should be given an opportunity to be heard. The Rejoinder also contends that MSEB in
their Reply have merely submitted that the review Petition is not maintainable,
without giving any grounds.
14. In their
Rejoinder, BESL have also sought to rebut with the help of hypothetical
figures, MSEB's claim that it is possible for all consumers to achieve a load
factor of 93% and avail of LFI to the maximum possible extent, i.e. 15%, through
the Commission's formula.
15. With regard to
rounding up, BESL have stated that it is the general practice to square up to
the next higher digit if a value is above 0.5%, and to the lower digit if it is
below 0.5%.
16. With regard to
marginal excess of Contract Demand, BESL have stated that the consumer is being
heavily penalized and, hence, there should be an allowance upto some percentage when Contract Demand is exceeded
due to compelling circumstances. The
Rejoinder illustrates BESL's practical difficulties by citing meter readings
From February, 2004. It states that
increasing the Contract Demand, as suggested by MSEB, is no solution since the
consumer would have to increase the demand further once again to achieve a
higher load factor. It also points out
that there is always a difference in the readings of MSEB's and their own meter
which should also be taken into account, the details of which are annexed to
the Rejoinder.
17. BESL also
reiterate that the provisions of the Order dated 10th March, 2004 cannot be
applied retrospectively, and the Rejoinder seeks to rebut MSEB's contention
that it would be difficult to pass on the benefit of incentives in the same
month.
18. The matter was
heard for admission on 3rd August, 2004.
Shri G.G. Basantani, Technical Consultant on behalf of BESL, accompanied
by Shri K. Sudesh Kumar of BESL, submitted at the outset that even if the
Commission found that the Petition did not meet the requirements of review,
then clarifications may be given on the Order dated 10th March, 2004 so as to
address BESL's concerns. Citing the
formula at para 32.1.3 (Part II) of the Order, he submitted that it was not
being applied properly by MSEB. According
to MSEB, 60 hours of interruptions or non supply was built into the formula. He contended that, if so, then the consumer
would not be able to achieve the maximum LFI.
Therefore, he contended that there was a lacuna in the formula. If it is in-built, he queried whether MSEB
would be deducting the excess over 60 hours.
In fact, they are dividing that figure by 720 hours also. Shri Basantani also submitted that the
number of hours of any kind of planned load shedding should be deducted.
19. Shri Basantani
reiterated that BESL had been deprived of LFI even when they had exceeded
Contract Demand by only 0.1%. He
pointed out that MSEB and BESL each have a meter at the same premises which,
though calibrated, had consistently been giving different readings. In February, 2004, according to the MSEB
meter, the Contract Demand was exceeded by 0.1%, but not according to BESL's
meter. He also pointed out that there
was no Contract Demand restriction on LFI in the Commission's operative Order
dated 1st December, 2003. In any case,
some tolerance level should be allowed in this regard, also taking into account
practical exigencies such as banking of capacitors, etc. BESL have suggested an upward allowance of
5%, but the Commission could fix any other reasonable percentage. As far as BESL's prayer for providing the
incentive in the same month, he acknowledged that the Commission has now
resolved the matter through its Clarificatory Order dated 13th July, 2004.
20. Ms. Ruby Kerawale,
Counsel for MSEB reiterated the contention in their written Reply that the
review Petition was not maintainable.
As far as any clarification was required, she submitted that MSEB had no
difficulty in conceding the prayer regarding rounding off to the next higher
digit in case of excess over 0.5%. The
Commission drew Counsel's attention to the difference in wording used in
respect of power factor incentive and LFI in its Order dated 10th March,
2004. In case of the latter, the
incentive is to be given "for every percentage point increase in load
factor from 85%". Thus, it is not
continuous but step-wise or discrete.
Moreover, a formula has been given for load factor and that will throw
up a specific figure. Around 8000 cases
might have to be reopened if such rounding off is agreed to, and the Commission
queried as to whether MSEB had considered the implications.
21. Shri C.B. Bagal,
Chief Engineer, (TRC), MSEB submitted that, as far as the difference in meter
readings was concerned, the acceptable range of error of electronic meters is
within + 0.5%. Shri Basantani
intervened to say that the differences between the readings on the two meters
are often more than that, and that they had taken up this problem in detail
with MSEB at the local level. MSEB had
stated that they were looking into it, nothing has been done. He had brought the correspondence with him,
and would furnish it to the Commission and to MSEB's representative. The Commission observed that if there is a
dispute regarding the accuracy of the respective meters, then BESL should
approach the appropriate authority.
However, if MSEB also recognizes that there is a problem, then they
should take immediate steps to resolve it.
22. Shri Basantani
reiterated BESL's contention that the restriction on LFI in case the Contract
Demand was exceeded was included for the first time in the Order dated 10th
March, 2004 and did not apply in February, 2004. The Commission observed that, while providing LFI in its
operative Order of 1st December, 2003, it was never its intention to mandate or
to condone a situation where Contract Demand is exceeded.
23. Referring to the
limit of 60 hours in the load factor formula, Shri Basantani submitted that the
excess number of hours should be deducted from the 720 hours. The Commission observed that, as far as the
maximum possible rebate is concerned, the Commission had only stated that the
total rebate would be subject to a ceiling of 15%, and not that it would
necessarily go upto 15%. Shri Basantani
submitted that at least the planned load shedding should be deducted, and that
they never informed about such load shedding.
Shri Bagal responded that BESL are an important consumer of MSEB in that
area, and that MSEB are not resorting to load shedding for them. However, MSEB have to resort to shut down
for a few hours of maintenance per month.
Shri Basantani submitted that at least those hours should be
deducted. The Commission observed that,
in such cases, MSEB should inform the consumers and treat it as planned shut
down to be considered while giving LFI.
Breakdowns, on the other hand, are not to be included and are already
considered in the formula.
24. The Commission
notes that Regulation 87 of the Conduct of Business Regulations, 2003 which
governed review of the Commission's orders at the time the Petition was filed,
reads as follows:
"Any
person aggrieved by a decision or order of the Commission, from which no appeal
is preferred or allowed, and who, from the discovery of new and important
matter or evidence which, after the exercise of due diligence was not within
his knowledge or could not be produced by him at the time when the decision/
order was passed by the Commission or
on account of some mistake or error apparent from the face of the record, or
for any other sufficient reasons, may apply for a review of such order, within
60 days of the date of decision/ order. to the Commission."
After the filing of the Petition, new
Conduct of Business Regulations have been notified on 10th June, 2004. However, Regulation 85 of the new
Regulations contains a similar provision.
Thus, the maintainability of the Petition has to be tested against these
requirements. The scope of review is,
accordingly, limited, and substantive modification of an Order outside its
scope can only be agitated in appeal and not before the Commission.
25. Keeping in view
the Regulations governing review, none of its elements have been cited to
justify introducing any allowance for exceeding Contract Demand for availing of
LFI since it would constitute a substantive modification in the LFI. No error has been shown, nor is their any difficulty
in implementing these provisions. In
its Order, the Commission has also brought out the reasons for not allowing any
LFI if the Contract Demand is exceeded.
As far as the claim that this restriction was not in the operative Order
dated 1st December, 2003 and, therefore, did not apply in February, 2004, the
Commission notes that the former is in the nature of a summary Order. Further details, modalities, elaborations
and considerations required in a speaking Order can necessarily be set out only
in the detailed Order, which followed on 10th March, 2004 and is, therefore,
applicable from the date when the summary Order took effect unless stated
otherwise.
26. With regard to the
prayer for squaring up to the next higher digit if the load factor is above
0.5%, para 32.1.3 of Part II of the Order dated 10th March, 2004 states that
"consumers having load factor over 75% upto 85% will be entitled to a
rebate of 0.75% on the energy charges for every percentage point increase
in load factor from 75% to 85%" (emphasis added). Thus, discrete and not continuous intervals
are envisaged. In other words, squaring
up can only be done to the lower digit unless there is a full percentage point
increase. The Order is clear on this
matter, and any change in this formulation is outside the scope of
clarification, particularly when the only ground cited is "general
practice", which is not relevant in view of the clear and precise wording
used in the Order.
27. There is nothing
in the Order to say that, in the best case, 15% LFI would be given. The Order only states that "the total
rebate under this head will be subject to a ceiling of 15% of the energy
charged to that consumer".
However, considering the submissions at the hearing, the Commission
clarifies that events such as stoppage for maintenance have to be treated as
planned shut down and be considered as such while computing entitlement for LFI
as per the formula.
28. As acknowledged by
BESL, in its Clarificatory Order dated 13th July, 2004, the Commission has
clarified that credit of the LFI and bulk discount is to be given to eligible
consumers for the relevant month in the energy bill pertaining to that month
itself. The Clarificatory Order also
states that, in case this practice is not being followed, it should be
implemented in the case of energy bills for the month of August, 2004 onwards.
The Commission rejects
admission of the Petition with the above observations and clarifications.
| Sd/- | Sd/- | Sd/- | |
| (Jayant Deo) | (Dr Pramod Deo) | (P. Subrahmanyam) |
|
| Member | Member | Chairman, MERC |
|
Sd/- |
|||
| (A.M. Khan) | |||
| Secretary, MERC | |||
|
|||