Before the
13th
floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005.
Tel. 22163964 /
22163965, Fax No. 22163976
E-mail mercindia@mercindia.com
Website: www.mercindia.com
In the matter of
Application dated 11.11.2002 filed by M/s Hanil Era Textiles Limited in respect of Transmission Loss and Maximum Demand Charges
for wheeling of captive power for third party sale.
Shri Jayant Deo, Member
Dr Pramod Deo, Member
Dated: June 02, 2003
M/s
Hanil Era Textiles Limited (HETL), village Vanivali, Patalganga, Taluka
Khalapur, District Raigad 410 220, have sought, under their Petition dated 11th
November 2002, that the Commission:
(a) issue an Order to the Maharashtra State Electricity Board (MSEB)
in respect of their existing wheeling agreement to extend determined amount of
credit for the Maximum Demand Charges in proportion to the Petitioner’s sale of
surplus electricity to M/s Bombay Dyeing or any other (one) industrial unit in
any manner whatsoever with effect from August 1998.
(b) declare and determine the amount of line loss being charged, with
the same reference period.
2. The Petitioner has approached the
Commission on the direction, based on consent terms filed by them and the
Respondent (MSEB) in the Court of the Civil Judge, Senior Division, Panvel in
Special Suit No. 42 of 2001 filed by the Petitioner. The Court directed HETL to
apply to the Commission:
“to determine as to whether the line losses from August 1998
onwards will be 5% as contended by the defendants [MSEB] or will be 1% as
contended by the plaintiff [HETL] or any other percentage between 1% and 5%…The
rate so fixed by MERC will be binding…and to determine as to what will be the
credit that the defendants will have to give to the plaintiff out of the
maximum demand charges proportionate to the electric power supplied by the
plaintiff to the Bombay Dyeing and Manufacturing Co. Ltd. from August 1998
onwards. The MERC will also decide the rate of credit to be given to the
plaintiff for maximum demand charges…The rate so fixed by MERC will be binding
on both the parties…”
3. Both parties were heard on 16.1.2003. Shri Mukesh Vashi, Counsel for the
Petitioner, submitted that theirs is a 100% Export Oriented Unit manufacturing
yarn. In order to avoid damage to the
yarn due to voltage fluctuation, HETL sought and were granted permission by
MSEB for installation of a Captive Power Plant (CPP) of 17.87 MVA to generate
electricity for their own use. Subsequently, in order to put to use the surplus
power from their CPP, HETL sought and were granted permission by Govt. of
Maharashtra (GoM) to sell power to a third party, namely M/s Bombay Dyeing
& Mfg. Co. Ltd. (BDMCL).
Accordingly, a tripartite agreement was entered into in 1998 between
HETL, BDMCL and MSEB for the sale of HETL’s surplus power upto a maximum of
41.27 lakh units per month to BDMCL through the MSEB grid. The agreement was renewed from time to
time.
4. Counsel for the Petitioner stated that
the dispute relates to (i) charging by MSEB of transmission loss from HETL at a
flat rate of 5% in the slab for losses upto 50 kms., and (ii) levy by them of
full maximum demand charges on BDMCL without passing on any share to the
Petitioner, although a part of BDMCL’s demand is met by HETL.
5. Petitioner’s Counsel contended that, as
implied by the term itself, transmission loss must be charged on the basis of
the actual loss occurring while transmitting the power. This actual loss has been computed and
certified by the Petitioner's Chartered Engineer as 1%. The appropriate slab for this would be 0.2%
per kM and therefore cannot exceed 1%.
He submitted that this is a matter of fact which has not been disputed
by MSEB in their reply. MSEB's only
argument is that the parties are bound by the agreement between them, in which
the transmission loss is considered as 5%.
Drawing attention to paras 5, 7, 11, and 12 of MSEB's affidavit-in-reply
dated 2.1.2003, he stated that the figure of 5% has been arrived at taking into
account average losses in the State right from the stage of generation, whereas
it should be based on the actual loss in any particular case. In any event, the overall average loss of
39% cannot be the basis on which the actual transmission loss in a particular
case can be charged. MSEB cannot make
profits taking recourse to the average loss.
5% is to be treated as the upper limit, but the amount charged has to be
on the basis of the actual loss if it is lower than this.
6. With regard to the transmission and
wheeling charges to be levied, HETL’s Counsel submitted that the concerned
Chief Engineer, Kalyan Zone was to determine these charges after ascertaining
the actual distance. This is clear from
the tripartite agreement, which provides that:
"The wheeling charges and transmission losses in terms of kwh
will be in terms of Hanil Era's account.
Upto 50 kms distance, the wheeling charges will be 2% of energy received
for wheeling and transmission losses will be 5% of energy received for
wheeling. Appropriate percentage of
wheeling charges and transmission losses will be decided by Sr. Engineer, MSEB
and CE, Kolhapur after ascertaining the actual distance of wheeling. Wheeling
charges and transmission losses in terms of kWh will be deducted from the units
received for wheeling as per Condition No.1 above and balance will be
considered as energy to be wheeled to Bombay Dyeing. This energy will be wheeled on 24-hour basis".
The surplus power exported by HETL
and received by BDMCL has to be metered, and hence the transmission loss must
be charged on the basis of actuals and not with reference to a slab or
averages. The only scientific method of
calculation of transmission loss would be the difference between the energy
accounted for at both the receiving and supply points.
7. Regarding the claim for a share in the
Maximum Demand (MD) charges, Counsel for the Petitioner submitted that MSEB is
recovering these from BDMCL. However,
they have not been passed on to HETL in proportion to the power supplied by
them, and for which they are entitled to credit.
8. With regard to the sanctity of the
agreement entered into by them, Counsel for the Petitioner stated that the
renewed agreements for 2001 and 2002 incorporated a provision that they would
be subject to the final decision on the dispute pending in the Civil
Court. In accordance with the consent
terms filed in Court, that dispute is now before the Commission. The Preamble to the Electricity Regulatory
Commissions (ERC) Act, read with Sections 22 and 29, make it clear that these
matters are within the Commission's jurisdiction, and also that commercial
principles would have to be applied in deciding them in view of the provisions
of Sections 22(1)(b) and 29(2). The
agreement provisions regarding the matters under dispute are primarily based on
Commercial Circulars of MSEB which are required to be, but have not so far been
approved by the Commission.
9. Counsel for the Petitioner also argued
further that the CPP consent holder is deemed to be a licensee. He cited the Supreme Court judgement in the
case of GRIDCO v. ICCL, where ICCL was held to be a licencee by virtue of the
permission granted by the Orissa Government for a CPP. Therefore, MSEB’s
argument that HETL cannot claim MD charges, not being a licensee, does not
hold. These are towards fixed charges, i.e. for providing the infrastructure
and making supply available. The fact
that a part of the supply to BDMCL is met by HETL justifies their claim for
passing on of the MD charges proportionately.
It would not be correct to say that the MD charges are levied in the
context of MSEB undertaking to meet the contract demand and making it available
upto the premises irrespective of whether or not the CPP consent holder is
feeding power to the system or not. In
this case, the tripartite agreement has been entered into precisely because of
MSEB's inability to supply adequate, reliable power. Moreover, MSEB are in any case paid as per the tariff for the
sanctioned standby power regardless of whether it is availed of or not.
10. Ms. Deepa Chawan,
Counsel for MSEB, submitted that HETL are supplying power to the MSEB grid for
BDMCL at 22 KV level, whereas MSEB are supplying power at the much higher level
of 220 KV to BDMCL. In addition, MSEB supplies some power independently to
BDMCL, who are also their consumer. For
the power supplied by HETL to BDMCL through the grid upto the permitted limit,
the charges are to be paid by BDMCL and not by MSEB. If HETL were to supply BDMCL directly, they would have been
required to step up from 22 to 220 KV.
11. In this background, MSEB Counsel stated
that, initially, HETL were permitted a CPP for their own use. In 1998, permission was given for sale to
BDMCL also. The arrangement is
different when a licensee sells power to a consumer. A licensee is licensed under the Indian Electricity (IE) Act to
supply to a particular consumer or area.
In this case, HETL are not doing so.
They are feeding power to the MSEB grid, and are not licensees. This arrangement is a working solution for
the surplus CPP power whereby the supplier is assured of payments from a third
party. In fact, in the year 2000, MSEB
had suggested that, instead of supplying to BDMCL, HETL could supply to MSEB
who would pay them, but they did not agree, and finally the agreement was
extended upto 2003 accordingly.
12. Counsel for MSEB
also submitted that the tripartite agreement constitutes a contract between the
parties, and cannot be challenged on grounds other than those set out in the
Indian Contract Act. Moreover, the
conditions stipulated in the agreement are not contrary to or inconsistent with
any Government policy or Commission directives. Its terms are, therefore, binding on the parties. The terms include payment of prescribed
wheeling charges and transmission losses on a distance slab basis.
13. She submitted that
there are several difficulties in trying to calculate exact transmission losses
in such a wheeling arrangement.
Moreover, HETL are supplying at 22 KV, whereas MSEB are doing so at 220
KV. The computations of the Chartered
Engineer (who is a Mechanical and not an Electrical Engineer) cited by the Petitioner
have overlooked this aspect. MSEB fixed
the distance slabs as a matter of policy, on an ascending scale. In fact, at the higher slabs, the actual
losses may be even more. This cannot be
challenged at this stage, after voluntarily entering into agreement. The tripartite agreement does not say that
recovery will be made on the basis of actuals. Ultimately, the transmission
losses MSEB would be entitled to charge in future, would be decided by the
Commission as and when it decides a policy for CPPs, after considering all the
technical details. Moreover, the
average loss level in the State grid is to the tune of 39%, whereas a maximum
of 10% transmission loss is recovered under the current policy based on the
distance slab in this case. Even the Commission,
as an interim arrangement, has allowed transmission loss and wheeling charges
at 5% and 2% respectively in its Order on non-fossil fuel based co-generation
projects.
14. Counsel for MSEB submitted that they
also have an independent contract with BDMCL for supply of power. HETL cannot argue on behalf of BDMCL for
reduction of contract demand or similar matters which have been determined with
MSEB even before the subsequent wheeling arrangements. The agreement shows that, whether or not
shut-downs are planned or unplanned, MSEB are obliged to supply power to BDMCL
and have to keep their infrastructure in place for the purpose. Clause 11 of the tripartite agreement cannot
be challenged by HETL since they do not represent BDMCL. Under this provision, BDMCL cannot reduce
their contract demand, and 50% of the contract demand or actual MD recorded
(whichever is higher) will be billed as per MSEB's tariff. Any separate arrangement for charges between
HETL and BDMCL would be their business.
Counsel also drew attention to Clause 14, which provides that the terms
and conditions of the existing agreement between MSEB and HETL, and between
MSEB and BDMCL for power supply from MSEB shall remain unchanged.
15. MSEB Counsel stated that the consent was
originally granted to HETL for installation of a CPP only for their own
requirements. Subsequently, the sale of
surplus power was allowed so that it is not wasted. The fixed charges incurred for setting up the CPP cannot be
recovered from MSEB by asking for a share of MD charges or in any other manner,
but has to be built into the costs.
This is a bilateral matter between HETL and BDMCL.
16. Counsel for MSEB submitted that a MD
charge can only be levied if there is a statutory or contractual right, and the
Petitioner has none. The statutory
right to recover such a charge is contained in Section 18 of the IE Act, which
permits licensees to levy annual charges.
The Petitioner is not a licensee within the meaning of the Act, which is
restricted to any person licensed to supply energy. Section 3 provides for the grant of licenses, and the State Govt.
has not granted any such licence to HETL to supply to BDMCL or to any
particular area. Similarly, under
Section 28 ,
“No person other than a licensee shall engage in the business of
supplying energy to the public except with the previous sanction of the State
Government and in accordance with such conditions as the State Government may
fix in this behalf, and any agreement to the contrary shall be void.”
In this
case also, HETL are not supplying electricity to the public and are not falling
within Sec.28. They supply electricity to the MSEB, which is wheeled to BDMCL.
Further, under the proviso to S. 22 of the I(E) Act,
“no person shall be entitled to demand, or to continue to receive,
from a licensee a supply of energy for any premises having a separate supply
unless he has agreed with the licensee to pay to him such minimum annual sum as
will give him a reasonable return on the capital expenditure.”
17. Counsel submitted that, since HETL are
not licensees, they do not have a statutory right, and cannot recover MD
charges from BDMCL even under any independent agreement. The Supreme Court judgement cited by him
relates to arbitration and other matters in the case of a licensee under the
provisions of the Orissa Electricity Reform Act, which is not related to the
definition under the ERC Act or the IE Act. It is, therefore, not relevant for
the purpose of determining whether the Petitioner in the present case can ask
for a share in the maximum demand.
18. Counsel for MSEB stated that, although
it is true that GoM policy does not stipulate such a restriction, the agreement
with the Petitioner subsists on a year-to year basis, and is renewable on
mutually agreed terms and conditions so as to enable policy changes to be
incorporated. Moreover, the Supreme
Court has held that State Govt. directives under Section 78A of the Electricity
(Supply) Act are not binding. She
submitted that the Commission’s Order in the matter of Sunflag Iron & Steel
Industries Ltd. laid down that any change / amendment in an existing Energy
Purchase Agreement would require its approval.
MSEB are bound to implement these directives, and would approach the
Commission in such circumstances unless a general policy directive is issued before this. Counsel also submitted that the Commercial
Circular on which the tripartite agreement was based had been issued prior to
the constitution of the Commission.
19. In reply, Counsel for the Petitioner submitted
that the tripartite agreement would be subject to the Commission's approval
under Section 22 of the ERC Act. With
regard to MSEB's challenge to the Chartered Engineer's certification, this is a
factual matter and has to be rebutted on merits. In their affidavit-in-reply, MSEB have stated nothing to show
that, in such an arrangement, the actual transmission loss cannot be
ascertained, or what the basis for the slab is. Moreover, with regard to the Petitioner's status, the State Govt.
has granted permission to HETL to generate power and supply the surplus to
BDMCL. This is an undisputed fact. Under Section 28, the State Govt. gives
permission after consulting MSEB.
Therefore, MSEB cannot claim that the Petitioner is not a licensee, that
he has not been granted permission under Section 28, and that hence is not
entitled to a share.
20. The Commission has considered the
documents furnished and the written and oral submissions made by both parties.
While there is merit in the argument that overall, average loss in the grid
alone cannot be the basis on which the actual transmission loss is charged in a
particular case, the level of transmission loss at different voltage levels of
the transmission network has to be scientifically evaluated. Since the power is
not exported through a dedicated line with input and output measurement at both
ends, it becomes a part of the larger pool and cannot be demarcated in a
distinct manner. In the interim, it would be prudent and practical to go by
transmission loss level mandated by the agreement, until it can be provided
with a stronger foundation taking into account load flow studies since the loss
level can vary depending on factors such as line length, material used, the
line network configuration, physical conditions such as temperature, line
loading condition, and the state of equipments used at various stages of power
conversion from generation to transmission to distribution and, finally, to
usage. The distance slab adopted by MSEB in their policy considers that there
will be lower losses at shorter distances, all else remaining the same, and has
been incorporated by agreement. The provision in the tripartite agreement
quoted by Petitioner’s Counsel referring to the distance has to be understood
in the context of the slab to be applied to the Petitioner, i.e. if the
distance is within 50 kms., then the transmission loss is to be taken as 5%.
Another benchmark is also available. The Commission, as an interim arrangement,
has allowed transmission loss and wheeling charges at 5% and 2% respectively in
its Order dated 16.8.2002 for non-fossil fuel based co-generation projects,
which corresponds to the charges agreed to in this case on the basis of the
slab system adopted by MSEB through Circulars which pre-date the Commission.
Thus, quite apart from the sanctity of the contract represented by the
tripartite agreement, the Commission finds that the balance of convenience is
in favour of the stand taken by MSEB in this case.
21. Since the introduction of the two-part tariff,
the trend has been to move towards a reasonable relationship with the average
cost of supply as mandated by the ERC Act. Fixed charges, though still below
actual costs, are recovered to meet the fixed costs incurred by the utility to
make power available as envisaged in the E(S) Act. In any case, irrespective of
whether HETL supplies power or not, MSEB are legally bound to meet the contract
demand of BDMCL by virtue of their independent agreement with the latter. BDMCL
are free to seek appropriate remedies, e.g. for reduction of their contract
demand with MSEB. HETL cannot take up cudgels or speak on behalf of the third
signatory to the tripartite agreement, who are a separate entity having an
independent agreement with MSEB.
22. The Commission finds no merit in the
argument that, by virtue of the tripartite agreement through which it provides
a part of BDMCL’s power requirements or permission from the State Government,
HETL has the status of a licensee within the meaning of the IE Act, more particularly
Sections 3, 18, and 28. Section 28, under which HETL have admittedly been
granted permission by the State Government, is intended for parties other than
licensees, and no claim is made that they have either acquired or even sought a
license under the other applicable provisions. The Supreme Court judgement
cited by Petitioner’s Counsel refers to the status of the CPP consent holder as
a licencee primarily with reference to Sections 2(e) and (f) read with Chapter
VI of the Orissa Reform Act, which has no nexus with the present case. That meaning does not flow from the
provisions relating to licences in the IE Act read on its own, or together with
the ERC Act. Therefore, as rightly contended by MSEB, the Petitioner, not being
a licencee, cannot claim any statutory right or entitlement for a portion of
the MD charges under section 22 of the IE Act.
The Commission disposes of the
present Petition accordingly.
| Sd/- | Sd/- | Sd/- | |
| (Jayant Deo) | (Dr Pramod Deo) | (P. Subrahmanyam) |
|
| Member | Member | Chairman, MERC |
|
Sd/- |
|||
| (A.M. Khan) | |||
| Secretary, MERC | |||
|
|||