Before the
World Trade Centre, Centre
No.1, 13th floor, Cuffe Parade, Mumbai 400 005.
Tel. No. 022 22163964/65/69
– Fax 022 22163976
E-mail mercindia@mercindia.com
Website: www.mercindia.com
In the matter of
Refund to Niramaya Medical Foundation
& Research Centre of excess amounts of Security Deposit, Service
Line Charges, Service Connection Charges and
Energy Charges.
Dr Pramod Deo,
Chairman
Shri A. Velayutham, Member
Dated: 22nd
March, 2005.
Citing Section 142 of the
Electricity Act (EA), 2003 read with Sections 47, 62(6), and 57(2), M/s
Niramaya Medical Foundation & Research Centre (NMF), Baramati, District
Pune, through its Director Dr Ashok Deshpande, has filed a Petition dated 10th
May, 2004 with the following prayers:
i)
The
Maharashtra State Electricity Board (MSEB)
be ordered to refund forthwith the excess amounts recovered from NMF,
with interest at bank loan rate, in respect of the following:
a)
Excess
amount of Rs. 6,21,555/- towards security deposit out of the amount of Rs.
6,86,000/- paid.
b)
Excess
amount of fixed service connection charges (SCC) of Rs 30,000/- and Service
Line Charges (SLC) charge of Rs. 98,000/-
c)
Excess
amount on account of 15% supervision charges, out of Rs. 50,000/- recovered
from NMF.
ii)
MSEB
be ordered to refund the excess amount of energy charges, including Electricity
Duty, recovered through monthly bills from the date of connection towards the difference between the amount
charged under wrong category HTP-VI, and the amounts to be charged at the
correct rate, i.e. under category HTP-II.
iii)
Compensation
may be given to NMF under Section 57(2) of EA, 2003.
2. According to the Petition, NMF was given a HT connection from
9th October, 2002 by MSEB, with connected load and contract demand
of 590 kW and 250 kVA respectively. NMF has alleged that, taking advantage
of their monopoly position, MSEB dictated terms according to which NMF had
to give an undertaking that the entire work required for making the supply
available would be carried out by NMF at its own cost.
The undertaking was given in view of the hospital's urgent need for
electricity. Thus, the entire work of laying supply lines
and service connection was carried out by NMF at its own cost. Inspite of this, again the following amounts, totalling Rs.8.64 lakhs, were required
to be paid by NMF before the supply was released:
a) Fixed Service Connection charges Rs.
30,000.00
b) Security Deposit Rs.
6,86,000.00
c) Service Line charges Rs. 98,000.00
d) 15% supervision charges for work and CTPT Rs.
50,000.00
NMF contends that the above
recovery was without any justification, and has pointed out that:
(a)
The
recovery of SLC and SCC was unwarranted and illegal since the entire cost of
carrying out the work involved had already been incurred by NMF.
(b)
The
recovery of Rs. 6.86 lakhs towards Security Deposit was arbitrary inasmuch as,
after the supply was obtained, monthly billing during the calendar year 2003
had never exceeded Rs. 65,000/-.
Therefore, MSEB should have refunded the excess Security Deposit as per
the principles laid down by the Commission in its Tariff Order. Thus, the amount of Rs. 6.21 lakhs collected
in excess should be refunded in lumpsum with interest at the bank loan
rate. However, MSEB have only shown a
willingness to give refund only to the extent of 30% of the refundable amount
as per their letter dated 8th January, 2004, and that too in
instalments through adjustment in energy bills.
(c)
With
regard to the amount of Rs. 50,000/- recovered against 15% supervision charges,
no explanation has been given as to why CTPT has been included, since metering
equipment, including CTPT was required to be provided by NMF. Therefore, supervision charges should be
worked out on a justified basis and the excess amount refunded.
3. NMF has also pointed out anomalies in the tariff charged by
MSEB. Although NMF’s connection has
been given under tariff category HTP-II, in practice the energy charges were
levied at Rs. 3.50 per unit applicable to HTP-VI, whereas the billing demand
charges have been levied at Rs. 3 per kVA as applicable to NMF’s category, i.e.
HTP-II. NMF has pointed out that both
charges should have been applied as per HTP-II. By erroneously levying energy charges at HTP-VI rate, MSEB are in
violation of Section 62(6) and have to refund the excess recovered with
interest. Compensation should also be paid in view of the provisions of Section
57(2).
4. NMF’s Petition states further that, subsequently it applied
for reduction of contract demand from 250 kVA to 100 kVA. This was sanctioned by MSEB on condition
that NMF replace its existing 315 kVA transformer with a 100 kVA transformer at
its cost. Apart from the cost of the
transformer itself, NMF also had to incur expenditure on its installation and
the procedures involved in approval by the Electrical Inspector. According to NMF, this replacement of
transformer was unnecessary, and an additional expenditure of Rs. 50,000/- had
to be incurred as a result.
5. In their Reply dated 17th June, 2004, MSEB have
stated that, as per their Conditions of Supply, SLC or the entire actual
capital expenditure, whichever is higher, is required to be paid by the
consumer. The consumer has the option
of undertaking the work himself and paying 15% material plus labour cost. MSEB have pointed out that the Commission
had considered a similar dispute with respect to SLC in Case No. 29 of 2003
(M/s Shree Om Estate Developers & Others), though no Order appears to have
been passed yet. In that case, MSEB had
made detailed submissions regarding their authority to recover SCC and SLC, and
set out the principles for execution of capital works by consumers against
payment of 15% supervision charges. These submissions would apply to the
present case also, and have also been minuted in the Record of Proceedings.
6. MSEB have stated that Security Deposit was recovered from
NMF at the outset, initially on an estimated basis. In such cases, being based on estimation, it is possible that the
amount recovered may be found to be in excess when actual consumption details
become available. Under MSEB’s
Conditions of Supply, whenever the security deposit exceeds the average amount
of six months' energy bills, then the excess is refunded through adjustments in
energy bills, upto 30% of the amount of such bills. In the NMF case, the estimated security deposit recovered was
admittedly found to be far in excess as compared to the monthly average
bills. As such, after NMF approached
MSEB, instructions were given to refund the excess to the extent and in the
manner provided for in the Supply Conditions.
7. In their Reply, MSEB have admitted that, although NMF was in
the HTP-II category, energy charges were being wrongly levied at the HTP-VI
rate. However, when this anomaly was
noticed, remedial action was taken, and NMF is now being levied both demand as
well as energy charges as per HTP-II.
The excess recovery is being refunded through adjustment in energy
bills.
8. The Reply states that, at the time of release of supply,
MSEB had advised NMF to install a 315 kVA capacity transformer to match its
contract demand at that time.
Subsequently, NMF reduced the contract demand to 100 kVA, but without
any change in connected load (which remains at 590 kW). MSEB have contended that, looking to the
connected load, there is a possibility
of NMF exceeding its contract demand.
In order to avoid such possibilities, MSEB generally insist in such cases for installation of a transformer with
a capacity commensurate with the contract demand.
9. It its Rejoinder dated 15th July, 2004, NMF has
stated that the submissions made by MSEB in Case No. 29 of 2003 in their
defence are not available to it.
However, considering the provisions not only of EA, 2003 but also of the
erstwhile Electricity (Supply) Act and Indian Electricity Act, NMF contends
that the Supply Conditions with regard to SCC, SLC and 15% supervision charges
are in conflict with the statutory provisions, and are unjustified,
unreasonable and arbitrary. As far as
the alleged provision in the Conditions of Supply with regard to the ceiling of
30% refund of excess security deposit through energy bills, NMF finds no such
provision. In fact, the quantum of
security deposit is prescribed in the Tariff Order and, accordingly, mention is
made regarding this in the Tariff Schedule.
Thus, MSEB’s dispensation is neither in accordance with their Conditions
of Supply nor with the statutes.
Outside of these, mere circulars issued by MSEB have no independent
legal status. With regard to excess
recovery of security deposit and energy charges, although these have been
admitted, MSEB have not yet worked out the total amount of refund payable, and
have also not explained the minor credit shown to have been partly adjusted in
the energy bill for June, 2004.
10. With regard to transformer replacement, NMF's Rejoinder
states that, instead of imposing an additional burden on the consumer by
requiring replacement of transformer, NMF could have been required to maintain
the proper CT ratio vis-à-vis transformer capacity and contract demand.
11. At the hearing held on 22nd November, 2004 Dr
Ashok Deshpande of NMF, assisted by Shri B.R. Khedkar of Akhil Bharatiya Grahak
Panchayat, summarised the facts, contentions and sequence of the case as set
out in the Petition. They added that,
with regard to the change of transformer that was insisted upon, there is no
such provision in the MSEB Supply Conditions.
This insistence seems to be based on some apprehension on the part of
MSEB's Vigilance Department which has not been communicated to them
12. NMF representatives stated that, after the Petition was
filed, MSEB had worked out the excess energy charges recovered on account of
wrongful tariff category application for adjustment against energy bills, but
NMF are entitled to interest on this amount from the time when HTP-VI rates
were wrongly applied.
13. Shri Patki, Counsel for MSEB admitted that, taking into
account the net dues, some amounts are to be refunded to NMF. As per Clause 22 of MSEB’s Conditions of
Supply, the refund of security deposit is to be effected in a particular
manner, and in instalments not exceeding 30% of the average monthly bill. To the Commission’s observation regarding
MSEB’s general condition requiring three months' security deposit being
over-ridden by the specific provisions of one billing cycle in the Tariff
Order, Shri Sunnapwar, Technical Director, MSEB clarified that the 3 months'
period was being applied earlier.
Thereafter, the relevant Tariff Order provisions are being
implemented. He pointed out, however,
that the Tariff Order is silent on the mode of refund. To that extent, MSEB's Supply Conditions
would apply. To another query of the
Commission regarding refund of dues on account of energy charges in one
lumpsum, MSEB Counsel submitted that, as mentioned in their Reply, the refund
is being made, but that usually such adjustments are made through energy
bills. If the adjustment required
exceeds the amount of energy bills, it spills over into the next bill.
14. With regard to the requirement to replace the transformer upon
reduction in contract demand, with connected load remaining the same, Counsel
for MSEB reiterated the stand contained
in their Reply. Shri Sunnapwar, TD
clarified further that, following the reduction in contract demand, if that
level is exceeded, a penalty can be levied. However, a higher transformer capacity results
in increase in losses for the system as a whole. Therefore, MSEB insisted that the transformer should be commensurate
with the reduced contract demand, although admittedly such a requirement may
not be in their Supply Conditions. The Commission observed that it could be understood if there is
were a significant increase in contract demand, and a commensurate transformer
is insisted upon. There is also a
penalty for exceeding contract demand. That
being the case, the Commission queried as to why it was necessary to insist
on transformer replacement in this case, and whether MSEB could show that
it was essential in order to control losses. Shri Sunnapwar submitted that it adds to reactive power also, and
that the technical details could be furnished. The Commission allowed one week to MSEB to
enable them to do so, which might also be useful while finalizing the Supply
Code Regulations. In this context,
the Commission also observed that MSEB seem to be implying that the level
of penalty fixed for exceeding contract demand does not give a sufficient
price signal. Shri Khedkar, on behalf
of NMF, submitted that measures to control exceeding contract demand could
be raised by MSEB during tariff proceedings and resolved, if this were the
concern. He pointed out that NMF has been maintaining
a power factor of one. Contract demand
has also not been exceeded. If it
is exceeded, it is so recorded. In
case MSEB wanted to introduce such a condition with regard to replacement
of transformers, they should have been done so through due amendment to their
Supply Conditions. As far as losses
are concerned, they are in any event to NMF's account as a HT consumer.
15. Shri Khedkar queried the basis of the initial amount of Rs.
6.86 lakhs demanded on an estimated basis as security deposit in order to
emphasize its arbitrariness, particularly since the subsequent billing amounted
to an average of only Rs. 40,000/- to Rs 50,000/- per month. According to him, the tariff Order provision
came into force in May 2000, allowing security deposit only to the extent of
average for one billing cycle.
Moreover, from November, 2002, the average bill of NMF had reduced even
further, thus making the 30% ceiling imposed by MSEB on such refund even more
disadvantageous to NMF.
16. As regards the excess recovery on account of application of
wrong energy tariff, Shri Khedkar submitted that it was also adjusted
over several months and not in lumpsum. Therefore, interest as claimed should be given. In this context, he suggested that MSEB’s billing
software needs to be checked, and that MSEB should be asked to file an affidavit
to the effect that such instances are not taking place elsewhere and affecting
a large number of HT consumers. He
mentioned that, had he himself, belonging to a consumer protection organization,
not looked at the figures, NMF on its own may not have been detected the anomaly
and taken up the matter with MSEB. There may be many other such consumers.
17. The Commission has considered the written and oral submissions
made in this case. With regard to the refund of excess security deposit originally
recovered on an estimated basis while releasing the connection, the Commission
notes that, in its second Tariff Order dated 10th January, 2002,
the Commission had reduced the amount of security deposit to the equivalent
of the average of three months of billing or a billing cycle period, whichever
is less. Thus, the security deposit
for HTP-II consumers would generally be equivalent to one month’s average
billing. Admittedly, MSEB have recovered
an amount far in excess of this initially on an estimated basis. The only issue in dispute is whether or not
NMF is entitled to refund in one lumpsum with interest. Prior to the Supply Code Regulations coming
into force, the Commission had not given any directions on this matter. On the other hand, MSEB’s Conditions of Supply
provide for any excess security deposit to be adjusted in installments, the
amount of which would not exceed 30% of the average monthly bill. Although MSEB’s earlier dispensation with regard
to the quantum of security deposit has been superceded by the specific provisions
in the second Tariff Order, the Commission has not interfered with the pre-existing
dispensation of MSEB with regard to how the excess recovered is to be refunded.
The Commission also notes that the Tariff Schedule booklets of MSEB
have from time to time also contained this provision, lastly in the Tariff
Booklet issued after the Commission’s last Tariff Order, and with the Commission’s
approval. Thus, if MSEB are strictly following those
provisions with regard to the manner of refund, there is no ground for the
Commission to interfere with it for the period uptil 20th January, 2005. On that date, however, the Commission notified
its Electricity Supply Code and other Conditions of Supply Regulations, 2005.
These Regulations over-ride MSEB’s existing dispensation inasmuch as,
under Regulation 11.5, the excess security deposit amount is to be refunded
in a single payment, either by way of adjustment in the next bill or by way
of separate cheque payment, at the option of the Applicant, within 30 days.
Therefore, by 20th February, 2005, MSEB should have refunded
the balance, if any, of any excess still remaining to NMF in full. If they
have not done so, such repayment should be made forthwith, alongwith due interest
for the period after the notification of the Supply Code.
18. As pointed out by MSEB, certain issues were raised by M/s
Shree Om Estate Developers & others regarding the SLC, SCC and ORC
dispensations of MSEB in Case No. 29 of 2003.
In its Order dated 10.8.2004 in that Case, the Commission has concluded
that:
“As acknowledged by their
Counsel, MSEB's challenge to the Commission's jurisdiction over the
dispensation and charges in respect of matters, such as these (arising from an
earlier Order) failed in the High Court.
MSEB were given time by the High Court to appeal to the Supreme Court,
but they did not do so. Consequently,
after a communication from the Commission, MSEB submitted a proposal on 26th
September, 2003 for approval of their Conditions and Miscellaneous Charges of
supply and various Circulars issued after the constitution of the
Commission. By that time, the EA, 2003
had come into force. Under the new Act,
the Commission is required to specify the Supply Code and related matters by Regulations,
and this exercise was initiated. In
fact, the draft Supply Code and related Regulations, which seek to
comprehensively address the matters raised by the Petitioner and the anomalies
and open endedness of the present practices followed by MSEB, have recently
been put to the public for comments by the Commission. There would, therefore, be a clear and
transparent dispensation after these Regulations are notified, i.e.
prospectively. Therefore, while
appreciating the issues raised by the Petitioner, and also keeping in view
MSEB's arguments that some of these charges are pre-existing and continue to
operate until they are duly revised by the Commission, the Commission is not
inclined to interfere in the matter of ORC and SLC retrospectively”.
However, the issues raised in that Case were somewhat
different from the present matter, inasmuch as NMF has challenged the validity,
even within the terms of MSEB's own dispensation, of recovering SCC and SLC
when the entire necessary infrastructure has been provided by NMF itself at its
own cost. At the hearing and in their
written submissions, MSEB have not squarely addressed this contention. In fact, in their Reply dated 17th
June, 2004, MSEB have stated that:
“As per the provisions of
the Board’s Conditions of Supply, any consumer approaching the Board for power
supply on High Tension is required to pay the Service Line Charges or the
entire actual capital expenditure whichever is more. It is also submitted that, in all such cases, the consumer is
given an option to carry out the work himself and pay 15% of the material plus
labour cost, however the consumer is never forced to carry out the work by
himself only."
In the circumstances of the
present case, it has not been explained why SCC and SLC have been charged in
view of the clear dispensation brought out above. On the other hand, supervision charges have also been levied on
the work done by NMF. Therefore, the
Commission finds no justification in the levy of SCC and SLC when NMF itself
has undertaken the infrastructure at its cost.
To that extent, the SCC and SLC should be refunded to NMF with interest
as would be applicable to delayed payments by HTP-II consumers, from the date
of such recovery till the refund to NMF.
19. With regard to supervision charges, MSEB’s Conditions of
Supply provide for recovery of 15% of the cost of material and labour. This has now been superceded by the proviso
to Regulation 3.3.8 of the Supply Code, under which supervision charges are to
be approved by the Commission, but cannot exceed 15% of the labour cost. However, the supervision charges levied by
MSEB in this case predate the Regulations, and were mandated by their Supply
Conditions. Moreover, since CTPT is very much a part of the material
cost involved, the Commission is unable to fault MSEB on this account.
20. MSEB have admittedly erred in levying energy charges at
a rate ( HTP-VI) different from the
tariff category accorded to NMF (HTP-II).
On this point also, the dispute only relates to the manner and time
within which refund is to be made.
Considering the circumstances of the case and in the absence of any
provision to the contrary in MSEB's Supply Conditions (unlike the refund of
excess security deposit), MSEB should have refunded the excess recovered
expeditiously, and with interest. The
Commission appreciates that there may sometimes be cases in which complexities
in the nature of operations and interpretation result in a wrong tariff
category being applied. In this case,
however, there was no such ambiguity.
MSEB applied the HTP-II category to NMF, and also billed demand charges
on that basis. In these circumstances,
there can be no mitigating explanation for the levy of energy charges at the
HTP-VI rate. Therefore, MSEB should
refund the balance remaining, if any, forthwith. Moreover, in addition to the principal amount, interest at the
rate applicable to delayed payments by MSEB's HTP consumers should also be paid
to NMF from the date of such wrongful recovery uptil the date of refund,
including in respect of the amounts already adjusted so far.
21. MSEB have not explained how it is possible for NMF to have
been billed at different tariff rates for demand charges and energy
charges. In the interest of both MSEB
and their consumers, MSEB should review their billing software or other
procedures responsible for such an anomaly, so that corrective measures are
taken and such instances do not arise.
22. NMF was allowed a reduction in contract demand. The connected
load remaining the same, MSEB insisted on the installation of a transformer
commensurate with the reduced contract demand.
Thus, having initially installed a transformer, NMF had to incur expenditure
again to replace it. While admitting that such a requirement was not duly
codified, MSEB have argued that requiring the consumer to do so in such circumstances
was justified on technical and commercial grounds. In response to the directions given at the
hearing, under their submission dated 4th December, 2004, MSEB have stated that:
"The transformer being
a total inductive load, under no load condition, the transformer feeds total
inductive power in the system. As a consequence the no load P.F. even drops to
10% to 20%. If we permit three times higher capacity transformer then no load
losses will be more than the proper capacity transformer losses.
For example, if we take
total contract demand of HT consumer of Maharashtra, i.e. 5540 M.W.
Three time capacity will be 16620 MW
1% Reactive component will
be added in MSEB system i.e. 166 MVAR. It amounts to less generation by 166 MW.
If we allow this to any one consumer, there will be no
discipline.
In view of the above, it may
not therefore, be advisable to allow all or any consumer to have his
transformer capacity substantially more than his Contract Demand."
Considering the context in which MSEB had been asked for
further submissions regarding their requirement of transformer replacement,
it was expected that a detailed worksheet indicating the iron and copper loss
(at full load) of 100 kVA and 315 kVA transformers, along with the calculation
of total losses at 100 kVA load in respect of the two transformers in this
case, would be furnished by MSEB to illustrate their contentions. However,
instead of giving a comparison of losses accordingly, MSEB have given a hypothetical
example to justify their stand, which
the Commission finds to be technically flawed.
The transformer is a static device used for transformation of power
from a higher voltage level (adopted for lowering the transmission / sub-transmission
loss) to a user level of voltage, or vice-versa. Normally, a typical distribution transformer,
as in this case, would have full load efficiency in the range of 98%, and
low-load efficiency of around 96%. Being
static equipment, transformers have a long life, and are chosen keeping future
load growth in mind. The power factor
of such transformers is fairly uniform (around 0.8 to 0.85) across the transformer
loading range of 30% to 100%. The no load loss (Iron Loss or magnetizing loss)
of a transformer is constant for any loading. However, the load loss (Copper
Loss) is directly proportional to the square of current (factor of loading
of the transformer) being carried in the transformer windings. Theoretically,
the efficiency of a transformer is optimum at the point of loading where the
no load loss is equal to the load loss, and transformers are designed keeping
this factor in mind. The present-day
distribution transformers are mainly designed to be optimally efficient at
a loading of around 50%. Therefore, a 315 kVA distribution transformer would
operate most efficiently when loaded to the extent of 150 kVA. Thus, compelling the consumer to load his transformer
at rated full load capacity means effectively that he is being asked to run
his equipment in an inefficient manner and thus incur recurring losses.
As regards the argument that low power factor, particularly at no load,
will affect the system, the Commission finds no real substance in it, since
normally power factor
corrective equipments (for
compensating reactive load, including that of transformer) are provided by the
HT consumers, so as to avoid incurring penalty, and to take advantage of
incentives for maintaining a better power factor. As regards the objective of
minimizing the possibility of theft, any consumer with malafide intentions can
play mischief even if a transformer of 100 kVA is installed. Moreover, the consumer himself, as much as
the licensee, would be concerned with energy efficiency at his end in his own
financial interest. Therefore, the Commission is of the view that he cannot be
forced to opt for a transformer size that is not optimal. The choice, meeting
well-established technical requirements, must be left with the consumer.
However, while finding that MSEB were not correct in insisting on NMF replacing
its transformer after contract demand was reduced, given the circumstances of
the case and MSEB’s perceptions, and the fact that all the actions have been
completed without prior challenge in the appropriate forum, and considering the
balance of convenience, the Commission treats the matter as closed. In future,
MSEB should not insist on transformer replacement in such cases, and instruct
their concerned officials accordingly.
23. NMF has also sought compensation on various counts, citing
the provisions of Section 57(2) relating to Standards of Performance. However, the relevant Regulations under
Section 57 were notified much later, on 20th January, 2005.
The Commission disposes of NMF's Petition with these
observations and directions.
| Sd/- | Sd/- | |
| (A. Velayutham) | (Pramod Deo) | |
| Member | Chairman, MERC | |
|
Sd/-
|
||
|
(A.M.
Khan)
|
||
|
Secretary,
MERC
|
|
|