13th
floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005.
Tel. 22163964 /
22163965, Fax No. 22163976
E-mail mercindia@mercindia.com
Website: www.mercindia.com
Review of Cap on
monthly recovery of FAC charges.
Dr Pramod Deo,
Chairman,
ORDER
Dated: 13th April, 2005.
In its Order dated 1st July, 2004 determining the tariff of M/s. Reliance Energy Ltd. (REL), the Commission, while setting out the formula for Fuel Adjustment Cost (FAC) charges, had observed that:
“The change in variable
cost of own generation and variable cost of power purchase should be considered
in FAC computations, subject to operational norms, i.e. Generation, Heat Rate
and Auxiliary Consumption approved by the Commission for DTPS, and the
generation and power purchase mix in line with the principles approved by the
Commission in the Order.”
The Commission has also
stipulated that-
“The total FAC
recoverable, as per the formula discussed above, should be recovered from the actual
sales in that period in Rs/kWh terms. If the T&D loss of BSES is higher
than the T&D loss level approved by the Commission, then the amount of FAC
corresponding to the excess T&D loss in units will be deducted from the
total FAC recoverable.”
Further,
with the intention of mitigating any sudden tariff shock to consumers,
the Commission had also provided that:
“The total FAC to be charged to the consumers during any year should not
exceed 10% of the variable component of tariff or increase in Consumer
Price Index (CPI) in a similar period, whichever is lower. In case, the
FAC chargeable during any month exceeds any of these limits, then the Licensee will carry forward
the variation in costs and recover through FAC charge in the future period.”
2. As
directed in the Tariff Order, on 29th September, 2004, REL submitted
computations of FAC charges for July, 2004 (i.e. the first month following the
Order) for approval, followed subsequently by further details and clarifications.
3. The
Commission finalized its vetting of FAC computation and conveyed its decision
to REL. Among other things, the
Commission stated, under letter dated 19th January, 2005, at Clauses
4.8 and 4.9 as follows:
"The Commission has
noted while assessing FAC Charge for June 2004 for TPC that considering these
aspects, the Commission is of the view that the linkage of cap on monthly FAC
Charge with increase in CPI needs to be reviewed in the case of TPC at an appropriate
time after following due process in view of TPC’s particular fuel mix. Pending
such review, the Commission has decided to delink the cap on monthly FAC Charge
to the increase in CPI in a similar period in respect of TPC. However, this may
necessitate adjustment at a later date if the linkage of monthly FAC Charge to
the increase in CPI in a similar period is upheld after the review.
Since REL meets a
significant part of its requirement by power purchase from TPC, the Commission
is of the view that the linkage of the cap on monthly FAC Charge with increase
in CPI will need to be reviewed in the case of REL also after following due
process. Pending such review, the Commission has decided to delink the cap on
monthly FAC Charge to the increase in CPI in a similar period in respect of
REL. However, this may necessitate adjustment at a later date if the linkage of
monthly FAC Charge to the increase in CPI in a similar period is upheld after
the review.
The ceiling based on 10% of
the variable component of tariff works out to 29.90 Paise/kWh considering the
revenue from energy charge at Rs. 1910 crore and consumption at 6381 MU for FY
2004-05 as considered in the Tariff Order. Thus, in order to avoid sudden
tariff shock to consumers, the ceiling on monthly FAC Charge will be 29.90
Paise/kWh for FY 2004-05. This means that the average energy charge in any
month cannot exceed 329.20 Paise/kWh (i.e. 299.30 + 29.90 Paise/kWh) for FY
2004-05.
Since FACkWh for
July 2004 is lower than the monthly cap on FAC Charge as above, the FAC Charge
is assessed at 3.9 Paise/kWh.
It is also further clarified
that in case the FAC amount is under recovered for any month in future due to application
of the cap, such under recovered amount shall be carried forward to future
period for inclusion as part of Adjustment for Over Recovery/Under Recovery
component of FAC. To compensate it for additional Working Capital requirement
attributable to deferred recovery of FAC due to application of monthly cap, REL
shall be entitled to recover working capital interest at actuals as per the
provisions of the Working Capital Interest (I) component of FAC."
Accordingly, the Commission initiated suo
moto a formal review of the provisions of its Tariff Order dated 1st
July, 2004 only to the extent of the cap on monthly FAC charge recovery related
to CPI.
4. At the
hearing held on 2nd February, 2005, Shri Prakash Beria of REL stated
that, apart from the considerations mentioned in the Commission's vetting of
FAC charges, local freight charges had increased considerably and were expected
to rise further, and the cost of imported coal has also risen. There was high volatility in crude oil
prices. None of these are at all or
adequately captured by the CPI.
Therefore, he welcomed the Commission's decision to review the cap. He also submitted that the other cap of 10%
of variable cost may also have
to be reviewed in the context of volatile prices. The Commission observed that the consumer
would have to pay at some stage, and the issue was how to strike a balance and
even out the burden appropriately, and noted REL's point regarding the variable
cost cap.
5. The Commission notes that similar review
proceedings were initiated suo moto in respect of the CPI-based cap on monthly
recovery of FAC charges by TPC, and Order issued by the Commission on 4th
April, 2005.
6. Considering the submissions made during these
proceedings, the Order dated 4th April, 2005 in respect of TPC
and the circumstances which became apparent while vetting REL's FAC computations
as a result of which this review was initiated, it is clear that the ceiling
on FAC based on CPI, which hardly captures the fuel (more so liquid fuel) cost movement, does not
benefit the consumer since he would eventually be burdened with a cumulative
shock, including interest, at the end of the day, considering the present
level and volatility in fuel prices and the power purchase of REL. Thus, not only would the purpose of the cap
be defeated, but REL's cash flow may also be affected, with possible impact
on service standards. Working capital
interest on the delayed recovery would also be finally reflected in future
tariff. The generation and power
purchase mix largely determines the fuel cost variation, and it would be in
the interest of both REL and their consumers that such variation is passed
through earlier rather than accumulating.
At the same time, a balance of convenience also has to be struck in
such circumstances between a tariff shock in any particular month, and an
accumulated burden at the end of the day.
The Commission believes that doing away with the CPI related ceiling
while retaining the other provisions in the Tariff Order, viz. of a ceiling
on monthly recovery of 10% of the variable component of tariff, would be fair
and equitable to both REL and their consumers, and also address the stated
purpose of the ceiling on monthly FAC recovery. Therefore, in modification
of the dispensation in this regard in the Commission's Tariff Order, the CPI-related
cap on monthly FAC recovery is removed. However,
as at present, the total FAC to be charged to the consumers by REL during
any year should not exceed 10% of the variable component of tariff. In case
the FAC chargeable during any month exceeds this limit, then REL will carry forward
the variation in costs and recover it through FAC charge in the future period.
| Sd/- | Sd/- | |
| (A. Velayutham) | (Pramod Deo) | |
| Member | Chairman, MERC | |
|
Sd/-
|
||
|
(A.M.
Khan)
|
||
|
Secretary,
MERC
|
|
|